The Vogel Creek Conveyance Improvement Project

Recent Activity
Status of the Vogel Creek Conveyance Improvement Project
Construction on the ultimate improvements to Vogel Creek is underway. The $9.4 million construction project should take approximately 300 "working days" to complete, typically about 30 months, depending on weather. In early 2007, the original construction budget of $9.8 million was reduced to $9.4 million due to the exclusion of the installation of the Inwood Forest golf cart bridges.
The construction contractor will determine the schedule and sequence of work.
> See construction schedule of work activity (4Q 2007)
(PDF, 136 KB, 10/15/2007)
> See Ultimate Project Schedule
If you have any questions, contact the Vogel Creek Team via e-mail or call the District at 713-684-4000.
> See Frequently Asked Questions About Construction
Ultimate Channel Conveyance Project
White Oak Bayou to Arncliffe Drive
 |
 |
Engineering:
 |
 |
Preliminary Engineering: Complete June 2004 |
 |
 |
Final Design: Approved and signed by the City of Houston, January 2006. |
|
 |
 |
Right-of-Way Acquisition:
 |
 |
Residential property – Complete |
 |
 |
Partial property – Complete |
 |
 |
Commercial property – Complete |
|
 |
 |
Utility Adjustment: Complete |
 |
 |
Environmental Permit: Complete, April 2005 |
 |
 |
Construction: Underway, May 2006 |
Phase I - Excavation Project (Complete December 2004)
Vogel Creek, from White Oak Bayou upstream to Cypress Grove Lane (east side of Vogel Creek)
 |
 |
Engineering: Status - Complete |
 |
 |
Right-of-Way Acquisition: Status - Complete |
 |
 |
Utility Adjustment: Status - Complete |
 |
 |
Environmental Permit: Permit not required for this phase of work. |
 |
 |
Construction:
 |
 |
Contractor: LECON, Inc. |
 |
 |
Cost: $204,303 |
 |
 |
Status - Complete |
|
Phase II – Excavation Project (Complete October 2005)
Vogel Creek, from Long Creek Drive upstream to Arncliffe Drive (east side of Vogel Creek)
 |
 |
Engineering: Status - Complete |
 |
 |
Right-of-Way Acquisition: Status - Complete |
 |
 |
Utility Adjustment: Status - Complete |
 |
 |
Environmental Permit: Permit not required for this phase of work |
 |
 |
Construction:
 |
 |
Contractor: Hard Rock, Inc. |
 |
 |
Cost: $278,445 |
 |
 |
Status: Complete |
|
|
 |
|
 |
 |
 |
 |
 |
Vogel Creek Conveyance Improvement Project

|
 |
|