Harris County Flood Control District home pageAbout the districtPrograms and projectsLearning centerMaps and exhibitsFrequently asked questionsDownloadsLinksNews and media events
Your opinion matters. Take our quick survey.
Capital Improvement Program
Major Projects
General Info
Armand Bayou
Brays Bayou
Clear Creek
Clear Creek - 2nd Outlet Channel
Cypress Creek
Greens Bayou
Halls Bayou
Hunting Bayou
Sims Bayou
Vogel Creek
White Oak Bayou
Major Studies
FloodWise
Geographic Information Systems
Greens Bayou Wetlands Mitigation Bank
Home Buyout
Model and Map Management
Property Management
Stormwater Quality
Trails and Our Bayous
Tree Planting Program
TS-Allison Recovery Project
Vegetation Management
Watershed Environmental
Baseline Program

The Vogel Creek Conveyance Improvement Project


Project Background
The Harris County Flood Control District entered into a contract with CivilTech Engineering, Inc. in April 2003, for the design of channel conveyance improvements on Vogel Creek between Arncliffe and its confluence with White Oak Bayou.

This project initially entailed the design of a concrete-lined channel within the existing right-of-way. While a concrete-lined channel would require less right-of-way than a grass-lined channel, it could diminish environmental values of the creek without proper environmental mitigation. The Texas Commission on Environmental Quality (TCEQ) was working with the District to investigate what level of habitat mitigation would be required if the project were constructed as a concrete-lined channel within the existing right-of-way.


Home Buyout Brings New Project Opportunities
As a result of Tropical Storm Allison in June 2001, a voluntary home buyout program within Arbor Oaks and Inwood Forest subdivisions was initiated by the District with financial participation from the Federal government. This voluntary program was in effect through December 2003, and resulted in the purchase of 213 homes, with a total cost of over $25.8 million.

Because of the large number of properties along the banks of Vogel Creek that were purchased through the Tropical Storm Allison Voluntary Home Buyout Program, the District was able to consider construction of a grass-lined channel instead of the originally planned concrete-lined channel. The grass-lined channel provides an opportunity to enhance the environmental quality of Vogel Creek through the creation of "pool and riffle" areas in the bottom of Vogel Creek and the planting of native trees. This plan was presented to, and well received by, the U.S. Army Corps of Engineers and other state and federal regulatory agencies in preliminary meetings.



What Are "Pool and Riffle" Areas?
Natural streams form in order to convey stormwater runoff and the sediment (particles of soils and other solids in the stream) produced by erosion. The complex natural processes that shape streams do not produce straight channels with a uniform cross-section and a continuous depth. Streams tend to form meanders in order to maintain an overall gradient that will transport their sediment and water in the most efficient manner. The tendency is for a stream to cut (remove soil) along the outside of a meander bend (the "cut bank") and to deposit sediment on the inside of the bend (the "point bar"). Since the water tends to move faster around the outside of a bend, it will scour a deeper "pool" within its channel at that location. As the channel straightens out between bends, it tends to slow its velocity slightly, getting somewhat shallower and wider. This shallow zone is known as a "riffle" because the water often splashes over rocks or other protrusions at or near the surface.

Channel Thrives, Life Thrives
In a healthy stream with a proper mix of pools and riffles, aquatic life can thrive. Fish common to streams are adapted to spend much of their time in the pools, which have cooler temperatures, higher dissolved oxygen, and greater sources of food. They will tend to spawn on the riffles, as their eggs need warmer water in which to incubate successfully.

The District is designing the new channel of Vogel Creek to encourage the re-formation of natural pool and riffle areas. This is a reflection of the District's commitment to provide flood damage reduction projects that work, with appropriate regard for community and natural values.


Implementing the Project
Once a flooding issue has been identified and the project has been included in the Capital Improvement Program, a project team is selected to take the project from an engineering study through construction. While the steps for each project are very similar, each has an individual set of circumstances.

Common steps for the Vogel Creek Conveyance Improvement Project include:
Devise the flood damage reduction project
Evaluate impacts and mitigation needs
Consider community input (seek support, opinions; keep the community informed)
Design the project
Determine the land to build it upon (either on existing right-of-way, or through land acquisition)
Secure permission to build (environmental, city/county development permits; interlocal agreements)
Remove physical obstructions (such as utilities, bridges, etc.)
Allocate funding
Select a contractor (through a bid and award process) and build



Devise the Flood Damage Reduction Project
What we've done:
Vogel Creek Master Drainage Plan, May 2000
Status:
Completed



Evaluate Impacts and Mitigation Needs
What we've done:
Detention basin constructed south of West Little York at White Oak Bayou (E500-06-00) to mitigate stormwater from improvements being made to Vogel Creek, 1999
Status:
Completed



Consider Community Input
What we've done:
Letter to residents, May 2007
Email updates to HOA Presidents/Civic Club Presidents, Quarterly
Construction postcard, April 2006
Open house for area residents, July 2006
What's next:
Continue quarterly email updates to HOA Presidents/Civic Club Presidents
Continue semi annual meetings with HOA Presidents/Civic Club Presidents
Continue semi annual letter to residents, next letter Fourth Quarter 2007



Design The Project
What we've done:
Submitted 90% plans for the Vogel Creek Conveyance Improvements to the City for review, July 2005
Final design plans approved by the City of Houston, January 2006
HCFCD completes the Vogel Creek Conveyance Improvements Project Manual, January 2006
Status:
Completed



Determine The Land To Build It Upon
What we've done:
All residential properties (including partial properties) have been acquired, December 2005
Agreement "in principle" with the Inwood Forest Gold Club, December 2005
Status:
Completed



Secure Permission To Build
What we've done:
Interlocal Agreement approved by Houston City Council and by Harris County Commissioners Court, January 2006
Obtained all necessary building permits from the City of Houston
Status:
Completed



Remove Physical Obstructions
What we've done:
SBC adjustments/relocations are underway, January 2006
TimeWarner Cable authorized to commence utility adjustments/relocations, January 2006
Easements granted to CenterPoint Gas & Electric, January 2006
Utility relocations/abandonments completed for the Vogel Creek Conveyance Improvements
Status:
Completed



Allocate Funding
What we've done:
Locally funded through the District's Capital Improvement Program (CIP)
Amount allocated to date: $23.1 million
Amount spent to date: $17.3 million
Status:
Completed



Select A Contractor And Build
What we've done:
Vogel Creek project approved to advertise for bid, January 2006
Awarded bid to Lecon, Inc., May 2006
Status:
Construction is underway

Vogel Creek Conveyance Improvement Project

Project Overview
About the Project
Project Background
Project Status
Vogel Creek Maps & Exhibits
Vogel Creek Images
Vogel Creek VR Panoramas
Vogel Creek FAQs
News & Information
Vogel Creek Downloads
Vogel Creek Contact Info
Harris County Flood Control District
Footer navigation Home About the District Programs and Projects Learning Center Maps and Exhibits Frequently Asked Questions Downloads Links News and Events Contact Us Employment Site map Terms, Conditions and Notices Privacy Policy Accessibility Search