Harris County Flood Control District home pageAbout the districtPrograms and projectsLearning centerMaps and exhibitsFrequently asked questionsDownloadsLinksNews and media events
Your opinion matters. Take our quick survey.
Capital Improvement Program
Major Projects
General Info
Armand Bayou
Brays Bayou
Clear Creek
Clear Creek - 2nd Outlet Channel
Cypress Creek
Greens Bayou
Halls Bayou
Hunting Bayou
Poor Farm Ditch
Sims Bayou
Vogel Creek
White Oak Bayou
Major Studies
FloodWise
Geographic Information Systems
Greens Bayou Wetlands Mitigation Bank
Home Buyout
Model and Map Management
Property Management
Stormwater Quality
Trails and Our Bayous
Tree Planting Program
TS-Allison Recovery Project
Vegetation Management
Watershed Environmental
Baseline Program

The Vogel Creek Conveyance Improvement Project


News & Information

A calendar of public meetings will be posted on this website as soon as they are scheduled.

Vogel Creek Updates

June 2008 Update
Ultimate Conveyance Improvement Project Construction 95% complete
As of June 2008, approximately 95 percent of the overall construction project is complete and HCFCD has spent $8.7 million of the $9.4 million construction budget to date. Construction highlights include: The Long Creek Lane Bridge and Arncliffe cul-de-sac are both complete and open to traffic. HCFCD is performing clean-up of the site and final inspection of the bridges and utilities with the City. All construction items are anticipated to be 100 percent complete by the end of July 2008.


November 2007 Update
Ultimate Conveyance Improvement Project Construction 70% complete
As of November 2007, approximately 70 percent of the overall construction project is complete and HCFCD has spent $6.59 million of the $9.4 million construction budget to date. Construction highlights include: excavation is 90 percent complete and the White Oak Bayou transition is also 90 percent complete only some cleanup remains. Construction on Long Creek Lane Bridge is 70 percent complete, with completion estimated for December 2007. The lift station at Long Creek Lane Bridge is actually in operation, now, and the channel through Victory Drive is 90 percent complete.


May 2007 Update
Ultimate Conveyance Improvement Project Construction 43% complete
As of May 2007, approximately 43 percent of the overall construction project is complete, and the District has spent $4,037,000 of the $9.4 million construction budget. Construction highlights include: the Maple Tree Bridge is complete and has been reopened to the public; Long Creek Lane Bridge is now closed and work is underway; the lift station at Long Creek Lane Bridge is 90% complete; and the channel through Victory Drive is 40% complete. (The original construction budget of $9.8 million has been reduced to $9.4 million due to the delay of the installation of the Inwood Forest golf cart bridges)


October 2006 Update
Ultimate Conveyance Improvement Project - Construction 15% complete
As of October 2006, approximately 15 percent of the overall construction project is complete, and the District has spent $1,458,000 of the $9.8 million construction budget. Construction highlights include: both the West Little York Bridge and the Maple Tree Bridge have been demolished and work is underway; construction crews have completed a large amount of the channel improvements from White Oak Bayou upstream to West Little York; and excavation has begun under the bridge at Victory.


August 2006 Update
Ultimate Conveyance Improvement Project Construction 10% Complete
As of August 2006, construction is 10 percent complete. Construction highlights include: the installation of the concrete channel lining at the confluence of Vogel Creek and White Oak Bayou is in progress; the proposed sanitary sewer along Arbor Oak Drive is in place and activated; the former Maple Tree Bridge has been removed, the excavation for the proposed bridge has been completed, and the drill shafts for the new bridge will be installed this month.


May 2006 Update
Ultimate Conveyance Improvement Project - Final Phase Contract Awarded
On March 21, 2006, Harris County Commissioners Court authorized the Harris County Flood Control District to award a $9,776,271 million construction contract to Lecon, Inc. to complete the final phase of the Vogel Creek Conveyance Improvements.

More...

March 2006 Update
Ultimate Conveyance Improvement Project - Bid and Award
Harris County Commissioners Court authorized the award of a $9.8 million construction contract to to complete the final phase of the Vogel Creek Conveyance Improvement Project.

More...

February 2006 Update
Ultimate Conveyance Improvement Project - Design
The design of the project has been completed.

More...

December 2005 Update
Ultimate Conveyance Improvement Project - Design
The channel design has been completed and CivilTech Engineering, Inc. (CEI) is now in the process of securing the required signatures from the utility companies and the City of Houston on the final design plans.

More...

September 2005 Update
Phase II Excavation Project Long Creek Lane to South of Arncliffe Drive
Construction work is substantially complete at this time. We anticipate the contractor, Hard Rock Inc. to be completed by the end of October.

More...

August 2005 Update
Phase II Excavation Project Long Creek Lane to South of Arncliffe Drive
Following the relocation of the live TimeWarner fiber optic cable and other unexpected weather delays, construction crews from Hard Rock Construction, Inc. began excavating on the Phase II project on July 26, 2005.

More...

June 2005 Update
Phase II Excavation Project Long Creek Drive to Arncliffe Drive
CenterPoint Electric, CenterPoint Gas, TimeWarner Cable and SBC each independently reported to the District that the utility work necessary for Phase II had been completed.

More...

May 2005 Update
Phase II Excavation Project Long Creek Drive to Arncliffe Drive
Utility work in the Phase II project area has been completed by CenterPoint Electric, CenterPoint Gas and TimeWarner Cable. SBC is anticipated to complete their work by June 5, 2005.

More...

March 2005 Update
Phase II Excavation Project Long Creek Drive to Arncliffe Drive
As mentioned in early March, all utility adjustment agreements were secured from the utility companies and approved by Harris County Commissioners Court for the Phase II Excavation Project.

More...

February 2005 Update
Phase II Excavation Project Long Creek Drive to Arncliffe Drive
The design of the Phase II Excavation Project from Long Creek Drive to Arncliffe Drive has been completed by CivilTech Engineering, Inc. and all necessary approvals required by the City of Houston to construct the project have been obtained.

More...

Vogel Creek Conveyance Improvement Project

Project Overview
Project Status
Vogel Creek Maps & Exhibits
Vogel Creek Images
Vogel Creek VR Panoramas
Vogel Creek FAQs
News & Information
May 2006 Update
March 2006 Update
February 2006 Update
December 2005 Update
September 2005 Update
August 2005 Update
June 2005 Update
May 2005 Update
March 2005 Update
February 2005 Update