Harris County Flood Control District home pageAbout the districtPrograms and projectsLearning centerMaps and exhibitsFrequently asked questionsDownloadsLinksNews and media events
Your opinion matters. Take our quick survey.
Capital Improvement Program
Major Projects
General Info
Armand Bayou
Brays Bayou
Clear Creek
Clear Creek - 2nd Outlet Channel
Cypress Creek
Greens Bayou
Halls Bayou
Hunting Bayou
Poor Farm Ditch
Sims Bayou
Vogel Creek
White Oak Bayou
Major Studies
FloodWise
Geographic Information Systems
Greens Bayou Wetlands Mitigation Bank
Model and Map Management System
Property Acquisition
Property Management
Stormwater Quality
Trails and Our Bayous
Tree Planting Program
TS-Allison Recovery Project
Vegetation Management
Watershed Environmental
Baseline Program

The Vogel Creek Conveyance Improvement Project


Ultimate Project Schedule
Grass-Lined Channel from White Oak Bayou
Upstream to Arncliffe


The Vogel Creek Conveyance Improvement Project is primarily a grass-lined channel that includes:
The significant enlargement of Vogel Creek, (now completed)
The replacement of West Little York Bridge (now complete)
The replacement of Maple Tree Bridge (now complete)
The replacement of Long Creek Bridge (now complete)
The replacement removal of Arncliffe Bridge (now complete)

> See Recent Activity

The Vogel Creek Construction Project was executed over a period of 300 working days. The Schedule of Work Activity is the best representation of how activities were sequenced as the work progressed

The Schedule was based on a minimum of 10 working days per month and included time for historical weather days, County holidays and weekends.

The District had a number of activities to complete before moving into the Construction Phase. Below is a historical record of this work.


Harris County Flood Control District
Pre-Construction Work Activity
Activity Duration Schedule Current Status
Master Drainage Plan including Alternatives Analysis   Complete, May 2000  
Negotiate/Award Design Contract   Complete, April 2003  
Preliminary Engineering   Complete, October 2004  
Design   Complete January 2006  

Other Project Participants (Critical Path Items)
Activity Duration1 Schedule Current Status
Permits
USACE Permit   Complete, April 2005  
COH Permits   Complete, January 2006  
COH Interlocal Agreement   Complete, January 2006  
ROW
ROW Acquisition   Start Date: February 3, 2004
Complete May 2006
County Attorney's office negotiated a potential settlement with IFGC, Complete May 2006
Utility Adjustments4
CenterPoint Electric   Start Date: October 7, 2004
Complete, September 2006
 
CenterPoint Gas   Start Date: October 7, 2004
Complete May 2006
 
SBC   Complete, May 2006  
Time Warner Cable   Complete, May 2006  

Harris County Flood Control District
Activity Duration Schedule Current Status
Bid and Award   Complete, May 2006 May 2006 Bid awarded to Lecon Inc. on 3/21/06. Performance and Payment bonds approved 5/02/06.
Construction 30 months, or 300 working days Start Date: May 2006 Construction Complete: August 2008



Vogel Creek Conveyance Improvement Project

Project Overview
Project Status
Recent Activity
Ultimate Project Schedule
Vogel Creek Maps & Exhibits
Vogel Creek Images
Vogel Creek VR Panoramas
Vogel Creek FAQs
News & Information
Vogel Creek Downloads
Vogel Creek Contact Info
Harris County Flood Control District
Footer navigation Home About the District Programs and Projects Learning Center Maps and Exhibits Frequently Asked Questions Downloads Links News and Events Contact Us Employment Site map Terms, Conditions and Notices Privacy Policy Accessibility Search