|
|
 |
 |
 |
The Vogel Creek Conveyance Improvement Project

Ultimate Project Schedule
Grass-Lined Channel from White Oak Bayou
Upstream to Arncliffe
The Vogel Creek Conveyance Improvement Project is primarily a grass-lined channel that includes:
 |
 |
The significant enlargement of Vogel Creek, |
 |
 |
The replacement of West Little York Bridge (now complete) |
 |
 |
The replacement of Maple Tree Bridge (now complete) |
 |
 |
The replacement of Long Creek Bridge (now complete) |
 |
 |
The replacement removal of Arncliffe Bridge (now complete) |
> See construction schedule of work activity (2Q 2008)
(PDF, 176 KB, 06/02/2008)
> See Recent Activity
The Vogel Creek Construction Project will be executed over a period of 300 working days. The Schedule of Work Activity is the best representation of how activities will be sequenced and is expected to be adjusted to conditions as the work progresses.
The Schedule is based on a minimum of 10 working days per month and includes time for historical weather days, County holidays and weekends.
The District had a number of activities to complete before moving into the Construction Phase. Below is a historical record of this work.

Harris County Flood Control District
Pre-Construction Work Activity |
| Activity |
Duration |
Schedule |
Current Status |
| Master Drainage Plan including Alternatives Analysis |
|
Complete, May 2000 |
|
| Negotiate/Award Design Contract |
|
Complete, April 2003 |
|
| Preliminary Engineering |
|
Complete, October 2004 |
|
| Design |
|
Complete January 2006 |
|
| Other Project Participants (Critical Path Items) |
| Activity |
Duration1 |
Schedule |
Current Status |
| Permits |
| USACE Permit |
|
Complete, April 2005 |
|
| COH Permits |
|
Complete, January 2006 |
|
| COH Interlocal Agreement |
|
Complete, January 2006 |
|
| ROW |
| ROW Acquisition |
|
Start Date: February 3, 2004 Complete May 2006 |
County Attorney's office negotiated a potential settlement with IFGC, Complete May 2006 |
| Utility Adjustments4 |
| CenterPoint Electric |
|
Start Date: October 7, 2004 Complete, September 2006 |
|
| CenterPoint Gas |
|
Start Date: October 7, 2004 Complete May 2006 |
|
| SBC |
|
Complete, May 2006 |
|
| Time Warner Cable |
|
Complete, May 2006 |
|
| Harris County Flood Control District |
| Activity |
Duration |
Schedule |
Current Status |
| Bid and Award |
|
Complete, May 2006 |
Bid awarded to Lecon, Inc. on 3/21/06. Performance and Payment bonds approved 5/02/06. |
| Construction |
30 months, or 300 working days |
Start Date: May 2006 |
Construction is underway |

|
 |
|
 |
 |
 |
 |
 |
Vogel Creek Conveyance Improvement Project

|
 |
|