|
|
 |
 |
 |
The Vogel Creek Conveyance Improvement Project

Ultimate Project Schedule
Grass-Lined Channel from White Oak Bayou
Upstream to Arncliffe
The Vogel Creek Conveyance Improvement Project is primarily a grass-lined channel that includes:
 |
 |
The significant enlargement of Vogel Creek, (now completed) |
 |
 |
The replacement of West Little York Bridge (now complete) |
 |
 |
The replacement of Maple Tree Bridge (now complete) |
 |
 |
The replacement of Long Creek Bridge (now complete) |
 |
 |
The replacement removal of Arncliffe Bridge (now complete) |
> See Recent Activity
The Vogel Creek Construction Project was executed over a period of 300 working days. The Schedule of Work Activity is the best representation of how activities were sequenced as the work progressed
The Schedule was based on a minimum of 10 working days per month and included time for historical weather days, County holidays and weekends.
The District had a number of activities to complete before moving into the Construction Phase. Below is a historical record of this work.

Harris County Flood Control District
Pre-Construction Work Activity |
| Activity |
Duration |
Schedule |
Current Status |
| Master Drainage Plan including Alternatives Analysis |
|
Complete, May 2000 |
|
| Negotiate/Award Design Contract |
|
Complete, April 2003 |
|
| Preliminary Engineering |
|
Complete, October 2004 |
|
| Design |
|
Complete January 2006 |
|
| Other Project Participants (Critical Path Items) |
| Activity |
Duration1 |
Schedule |
Current Status |
| Permits |
| USACE Permit |
|
Complete, April 2005 |
|
| COH Permits |
|
Complete, January 2006 |
|
| COH Interlocal Agreement |
|
Complete, January 2006 |
|
| ROW |
| ROW Acquisition |
|
Start Date: February 3, 2004 Complete May 2006 |
County Attorney's office negotiated a potential settlement with IFGC, Complete May 2006 |
| Utility Adjustments4 |
| CenterPoint Electric |
|
Start Date: October 7, 2004 Complete, September 2006 |
|
| CenterPoint Gas |
|
Start Date: October 7, 2004 Complete May 2006 |
|
| SBC |
|
Complete, May 2006 |
|
| Time Warner Cable |
|
Complete, May 2006 |
|
| Harris County Flood Control District |
| Activity |
Duration |
Schedule |
Current Status |
| Bid and Award |
|
Complete, May 2006 |
May 2006 Bid awarded to Lecon Inc. on 3/21/06. Performance and Payment bonds approved 5/02/06. |
| Construction |
30 months, or 300 working days |
Start Date: May 2006 |
Construction Complete: August 2008 |

|
 |
|
 |
 |
 |
 |
 |
Vogel Creek Conveyance Improvement Project

|
 |
|