2018 Bond Program

Spring Creek - Bond Program

* Public input will continue to be an important part of the Bond Program. The Bond Program Project List currently includes 38 projects that were added as a result of Community Engagement Meetings held across Harris County in June, July and August, 2018. A meeting was held for each of Harris County’s 22 watersheds and in the Halls Bayou watershed (a tributary to Greens Bayou).

> Spring Creek Watershed Community Engagement Summary

An informational meeting was held for the Spring Creek watershed:

June 27, 2018
6 p.m. to 8 p.m.

Big Stone Lodge at Dennis Johnston Park
709 Riley Fuzzel Rd
Spring, Texas  77373

VIDEO: Opening Remarks

The map below shows the approximate location of proposed flood risk reduction projects in this watershed that could be eligible for bond funding.

> Enlarge Map (PDF)

> INTERACTIVE MAP: see potential projects in your area

Spring Creek Watershed Facts

Area (sq miles) Population* Structure Count** Harvey Damaged Structures***
Inside the 1% (100-year) FEMA floodplain 12.6 3,176 650 125
Inside the 0.2% (500-year) FEMA floodplain 3.5 2,525 1,963 349
Outside the 0.2% (500-year) FEMA floodplain 42.9 32,214 20,926 37
TOTAL 59.0 37,915 23,539 511

*Census 2010, **HCAD 2016, ***HCFCD final estimates as of June 2018

Median Family Income* $71,000 Median House Value* $219,000

* 2016 Census Data

The actual timing of individual projects will depend on a variety of factors including environmental permitting and right-of-way acquisition. Projects will be authorized individually for funding by Harris County Commissioners Court, based on recommendations by the Flood Control District.