2018 Bond Program

Spring Gully and Goose Creek - Bond Program

* Public input will continue to be an important part of the Bond Program. The Bond Program Project List currently includes 38 projects that were added as a result of Community Engagement Meetings held across Harris County in June, July and August, 2018. A meeting was held for each of Harris County’s 22 watersheds and in the Halls Bayou watershed (a tributary to Greens Bayou).

> Spring Gully and Goose Creek Watershed Community Engagement Summary

An informational meeting was held for the Spring Gully and Goose Creek watershed:

June 28, 2018
6 p.m. to 8 p.m.

Baytown Community Center
2407 Market Street
Baytown, Texas 77520

VIDEO: Opening Remarks

The map below shows the approximate location of proposed flood risk reduction projects in this watershed that could be eligible for bond funding.

> Enlarge Map (PDF)

> INTERACTIVE MAP: see potential projects in your area

Spring Gully & Goose Creek Watershed Facts

Area (sq miles) Population* Structure Count** Harvey Damaged Structures***
Inside the 1% (100-year) FEMA floodplain 6.2 7,463 3,624 536
Inside the 0.2% (500-year) FEMA floodplain 4.0 8,921 4,362 504
Outside the 0.2% (500-year) FEMA floodplain 22.6 35,843 19,880 1,037
TOTAL 32.8 52,227 27,866 2,077

*Census 2010, **HCAD 2016, ***HCFCD final estimates as of June 2018

Median Family Income* $50,000 Median House Value* $92,000

* 2016 Census Data

The actual timing of individual projects will depend on a variety of factors including environmental permitting and right-of-way acquisition. Projects will be authorized individually for funding by Harris County Commissioners Court, based on recommendations by the Flood Control District.