C-05 South Belt Stormwater Detention Basin A520-03-00

C-05 South Belt Stormwater Detention Basin A520-03-00

Last Modified: 05/12/2020 12:24 PM

Menu

Recent Actions

May 19, 2020 – Harris County Commissioners Court approved updates to project details in the 2018 Bond Program List. Update changes project title to include Unit ID; project funding also updated based on engineer's estimate and consolidation with Bond ID F-03; and project type changed because no funding partner has been identified. Additionally, a $175,843 agreement was authorized with an engineering firm for materials engineering and testing services and a $91,807 agreement was authorized for design, bidding, and construction phase engineering services for this project.

May 2020 – Construction began.

April 28, 2020 – Harris County Commissioners Court authorized negotiations with an engineering firm for materials engineering and testing services in support of this project.

November 12, 2019 – Harris County Commissioners Court authorized negotiations with various political jurisdictions for agreements in support of collaborative efforts to implement the Clear Creek federal flood damage reduction project and Clear Creek watershed bond projects.

December 4, 2018 – Harris County Commissioners Court approved a $188,180 agreement with an engineering firm for final design of this project.

Project Description

This bond project includes Phase 3 design and construction to expand the South Belt Stormwater Detention Basin (HCFCD Unit A520-03-00). Stormwater detention basins reduce flooding risks and damages during heavy rain events by safely storing excess stormwater and slowly releasing it back to the bayou when the threat of flooding has passed. The basin provides stormwater storage needed for mitigation of expected increases in stormwater flows resulting from future channel improvements to Beamer Ditch (HCFCD Unit A120-00-00, also known as Mud Gully), Turkey Creek (HCFCD Unit 119-00-00), and other projects. The basin is ultimately designed to hold up to 1,550 acre-feet or 505 million gallons of stormwater.

Location

This project is located on a 174-acre site on Beamer Ditch/Mud Gully, near the intersection of Beamer and Dixie Farm roads in the Clear Creek watershed of southeast Harris County.

Stage

Phase 3 of the basin excavation is currently under construction.

Bond Listing

Bond Project C-05 is a potential Partnership project. Total allocation for Phase 3 of the basin is currently $15.95 million on the Bond Project List, of which approximately $11.96 million would be partnership funding, if granted, and $3.99 million would be local costs. If partnership funds are not available, the project will be funded totally from the 2018 Bond Program as a “Local Only” project.

Milestones

Phase 2 

• This phase expanded the basin to include basin compartments south and west of the Phase 1 compartment. 

• Construction began in November 2016 and was substantially complete in 2019. 

• Harris County Commissioners Court awarded a $15.78 million construction contract to James Construction Group LLC for Phase 2 of the basin project. 

• The project continued the partnership between Harris County Flood Control District and Galveston County. 

Phase 1 

• This phase included excavation of the basin compartment northeast of Beamer Ditch/Mud Gully. 

• Construction began in late September 2014 and was complete in 2018. 

• Harris County Commissioners Court awarded an approximately $3.46 million construction contract to low bidder Trans-Global Solutions Inc. 

• The project was a partnership between the Harris County Flood Control District and Galveston County. Galveston County pledged up to $10 million of total basin construction costs. 

• Construction costs for Phase 1 were shared equally by the Flood Control District and Galveston County.

Bond Listing

List of 2018 Bond Projects


The Harris County Flood Control District has a significant number of flood damage reduction projects occurring all over Harris County as part of its on-going Capital Improvement Program (CIP), Operations and Maintenance, and the 2018 Bond Program. Click on the red and orange highlighted areas to learn about projects' details. Some early-stage projects are not highlighted in the map. The map will be updated when projects advance or when more information becomes available. 

• Maintenance Projects   
• Capital Projects

Project Lifecycle

Every flood damage reduction project is unique. Yet each project begins and ends, with common and predictable milestones along the way. Whether a project moves forward – and how quickly – depends on many factors, including the availability of funding at each milestone, shifting community priorities for flood damage reduction, and other changing circumstances (such as the price of trees or concrete) from year to year.

Read more...

COMMUNITY ENGAGEMENT MEETING

A Community Engagement meeting for this project was held on April 15, 2019.