CI-62 and CI-63 FM 528 and Dixie Farm Road

Project Description

Investigation to identify locations for new stormwater detention basins along lower Clear Creek, HCFCD Unit A100-00-00, near F.M. 528 and Dixie Farm Road

Recent Action

November 12, 2019 – Harris County Commissioners Court authorized negotiations with various political jurisdictions for agreements in support of collaborative efforts to implement the Clear Creek federal flood damage reduction project and Clear Creek watershed bond projects

November 13, 2018 – Harris County Commissioners Court approved a $260,000 agreement with an engineering firm for conduct an engineering investigation in support of this project

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to conduct an engineering investigation in support of this project

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project