CI-62 Study of Flood Mitigation Near FM 528 and FM 1959 in Friendswood

CI-62 Study of Flood Mitigation Near FM 528 and FM 1959 in Friendswood
Menu
Note: Bond ID CI-63 has been consolidated with Bond ID CI-62.

Recent Actions

January 4, 2022 –- Harris County Commissioners Court authorized negotiations with an engineering firm to provide engineering services in support of this project.

September 14, 2021 – Harris County Commissioners Court approved $163,568 for materials engineering and testing services in support of this project.

May 19, 2020 – Harris County Commissioners Court approved updates to project details in the 2018 Bond Program List. Update changes project title and funding to reflect consolidation with Bond ID CI-63

December 20, 2019 – Study complete.

November 12, 2019 - Harris County Commissioners Court authorized negotiations with various political jurisdictions for agreements in support of collaborative efforts to implement the Clear Creek Federal Flood Risk Management Project and Clear Creek watershed bond project.

November 13, 2018 – Harris County Commissioners Court approved a $260,000 agreement with an engineering firm to conduct an engineering investigation in support of this project.

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to conduct an engineering investigation in support of this project.

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project.

Engineering Report

Final Study Report

PROJECT LIFECYCLE

Every flood damage reduction project is unique. Yet each project begins and ends, with common and predictable milestones along the way. Whether a project moves forward – and how quickly – depends on many factors, including the availability of funding at each milestone, shifting community priorities for flood damage reduction, and other changing circumstances (such as the price of trees or concrete) from year to year.