C-16 Design and Construction of Woodland Trails Stormwater Detention Basin

C-16 Design and Construction of Woodland Trails Stormwater Detention Basin
Menu

Recent Action

October 13, 2020 – Harris County Commissioners Court authorized the application for a loan for funding for this project through the Texas Water Development Board-Flood Infrastructure Fund 2020 Program in the amount of $57,130,515, with a local contribution of $7,750,000.

May 19, 2020 – Harris County Commissioners Court approved updates to project details in the 2018 Bond Program List. Update changes funding based on HMGP Grant Application amounts.

September 25, 2018 – Harris County Commissioners Court authorized and initiated this project

September 25, 2018 – Harris County Commissioners Court authorized submission of an amended application to the Texas Department of Public Safety for a grant in support of this project