  • January 4, 2022 –Harris County Commissioners Court approved a Change in Contract No. 3 with an engineering firm adding 22 calendar days with no change to the contract amount in support of Phase 4 channel conveyance improvements.
  • January 7, 2020 – Harris County Commissioners Court awarded a $6.48 million contract for construction of this phase.

PROJECT DESCRIPTION

This project is to construct 4,790 linear feet of channel conveyance improvements along the Berry Bayou Tributary C106-03-00 from east of IH-45 along Shawnee Street going south to Edgebrook Drive.