F-37 M124-00-00 Conveyance Improvements

F-37 M124-00-00 Conveyance Improvements
Menu

PROJECT DESCRIPTION

This project includes the design and construction of channel conveyance improvements on Willow Creek tributary M124-00-00.

Recent Action

January 7, 2020 – Harris County Commissioners Court authorized negotiations with an engineering firm for materials engineering and testing services in support of channel excavation January 7, 2020 – Harris County Commissioners Court authorized the acquisition of six tracts of land in support of this project

December 17, 2019 – Harris County Commissioners Court approved a land exchange and $782,444 payment to acquire 22.889 acres for channel conveyance improvements and stormwater detention in support of this project.

September 24, 2019 – Harris County Commissioners Court authorized negotiations with Harris County concerning construction of a regional stormwater detention basin along Willow Creek Tributary M124-00-00 in support of this project.

July 30, 2019 – Harris County Commissioners Court authorized a $1.6 million agreement with an energy company to adjust pipelines in connection with this project 

April 30, 2019 – Harris County Commissioners Court authorized the Harris County Flood Control District to submit an application to the U.S. Department of Commerce/Economic Development Administration for a $3 million grant, with a required match of $3.5 million, for the Willow Creek Stormwater Detention Basin project 

November 13, 2018 – Harris County Commissioners Court approved a $901,245 agreement with an engineering firm to conduct preliminary engineering in support of this project 

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm for preliminary engineering and final design of this project

Conveyance improvements along HCFCD Unit M124-00-00, from State Highway 249 to Willow Creek

The Harris County Flood Control District has a significant number of flood damage reduction projects occurring all over Harris County as part of its on-going Capital Improvement Program (CIP), Operations and Maintenance, and the 2018 Bond Program. Click on the red and orange highlighted areas to learn about projects' details. Some early-stage projects are not highlighted in the map. The map will be updated when projects advance or when more information becomes available. 

• Maintenance Projects   
• Capital Projects