SEDIMENT REMOVAL AND DRAINAGE SYSTEM REPAIRS IN PRECINCT 2



SECOND GROUP 

In August 2018, the Flood Control District began work on a group of 14 maintenance projects in the Armand Bayou, Greens Bayou, Jackson Bayou, Spring Gully & Goose Creek, and Luce Bayou watersheds of east Harris County. This is the second group of projects in an $8.1 million construction contract to repair erosion, remove and dispose of sediment accumulations, and replace damaged drainage features such as stormwater outfall pipes and associated inlets, in order to restore overall drainage system function and stormwater conveyance capacity.

Second Group, Project Sites: 

Tributary of Greens Bayou – HCFCD Unit P138-05-00-X002 Entire channel, from its confluence with HCFCD Unit P138-00-00 (Hollyvale Drive) to its upstream limits (Casa Grande Drive) 

Tributary of Luce Bayou – HCFCD Unit S101-00-00-X001 Entire channel, from near E. Lake Houston Parkway to upstream end of the channel 

Tributary of Gum Gully in the Jackson Bayou Watershed – HCFCD Unit R102-03-00-X005 From 1,500 feet upstream of the confluence with Gum Gully (Wherry Drive) to near 500 feet downstream of F.M. 2100 (Reef Way) 

Tributary of Gum Gully in the Jackson Bayou Watershed – HCFCD Unit R102-03-01-X002 From F.M. 2100 and downstream 100 linear feet 

Tributary of Jackson Bayou – HCFCD Unit R103-00-00-X004 From the UPRR crossing to Crosby Lynchburg Road 

Tributary of Halls Bayou in the Greens Bayou Watershed – HCFCD Unit P118-36-00-X007 At the confluence with Halls Bayou 

Tributary of Goose Creek – HCFCD Unit O126-00-00-X003 From Omaha Street to upstream end of the channel 

Tributary of Goodyear Creek in the Greens Bayou Watershed – HCFCD Unit P103-03-00-X002 Entire channel from its confluence with Goodyear Creek to near Granada Street 

Willowspring Creek in the Armand Bayou watershed – HCFCD Unit B112-00-00-X009 From Spencer Highway upstream 2,000 linear feet 

Big Island Slough in the Armand Bayou Watershed – HCFCD Unit B106-00-00-X011 Near Clairmont Lane 

Willowspring Creek in the Armand Bayou Watershed – HCFCD Unit B112-00-00-X010 From Barry Oaks Lane to 200 feet upstream of Venture Lane 

Tributary of Horsepen Bayou in the Armand Bayou Watershed – HCFCD Unit B104-03-00-X009 From confluence with B104-03-01 to confluence with B104-03-02 

Tributary of Horsepen Bayou in the Armand Bayou Watershed – HCFCD Unit B104-03-02-X004 From Cranbourne Drive to El Dorado Boulevard 

Ditch #22 DD-5 in the Armand Bayou Watershed – HCFCD Unit B115-00-00-X011 From its confluence with Armand Bayou to Space Center Boulevard



FIRST GROUP

Work on a previous group of 15 sediment removal and erosion repair projects began in 2017 and was complete in 2018. (Map and list of sites below.) These projects were in the Sims Bayou, San Jacinto & Galveston Bay, San Jacinto River, Carpenters Bayou, Spring Gully & Goose Creek, Greens Bayou and Jackson Bayou watersheds of east Harris County. 

Sediment is soil that is broken down, carried and deposited by stormwater. Sediment accumulation, which can reduce stormwater conveyance capacity, is a particular issue in Harris County Precinct 2, which is geographically located on the downstream end of several watersheds. 

Planning for this first batch of projects began in early 2017. The Flood Control District partnered with Harris County Precinct 2 to prioritize and construct these and future maintenance projects in a phased approach that addresses watershed needs across the precinct. On September 12, 2017, Harris County Commissioners Court awarded an approximately $8.1 million construction contract to low bidder Choctaw Construction Services LLC. 

Construction equipment will access the work areas from multiple points along the selected project sites. The contractor will use heavy construction equipment such as dump trucks, backhoes and bulldozers. Motorists and pedestrians are encouraged to be alert to heavy equipment traffic when passing near construction access points. The Flood Control District appreciates your patience during these maintenance projects.

First Group, Project Sites: 

Tributary of Halls Bayou - HCFCD Unit P118-21-00-X003 From confluence with Halls Bayou, HCFCD Unit P118-00-00, to Isom Street 

Tributary within the Greens Bayou Watershed - HCFCD Unit P138-01-00-X004 Entire channel, from confluence with Ditch No. 9, HCFCD Unit P138-00-00, near Lauder Stormwater Detention Basin, HCFCD Unit P500-06-00, to near Sandydale Lane 

Tributary within the Greens Bayou Watershed - HCFCD Unit P138-01-01-X004 Entire channel, from confluence with HCFCD Unit P138-01-00 to near Ponder Lane 

Tributary of Rodgers Gully - HCFCD Unit G103-24-04-X005 Entire channel, from confluence with HCFCD Unit G103-24-00 to near Encenada Green Trail 

Tributary of Gum Gully - HCFCD Unit R102-10-00-X001 Entire channel, from confluence with Gum Gully, HCFCD Unit R102-00-00, to Miller Wilson Road 

Tributary of Gum Gully - HCFCD Unit R102-06-00-X001 Entire channel, from confluence with Gum Gully, HCFCD Unit R102-00-00, to Miller Wilson Road 

Tributary of Gum Gully - HCFCD Unit R102-03-01-X004 Entire channel, from confluence with HCFCD Unit R102-03-00 to Miller Wilson Road 

Tributary within the Jackson Bayou Watershed - HCFCD Unit R110-00-00-X001 From near Miller Wilson Road along the Union Pacific Railroad tracks to the end of the channel near Ramsey Road 

Tributary within the Goose Creek Watershed - HCFCD Unit O117-00-00-X007 Entire channel, from confluence with Goose Creek, HCFCD Unit O100-00-00, to Wade Road 

Tributary within the Goose Creek Watershed - HCFCD Unit O125-00-00-X002 Entire channel, from confluence with Goose Creek, HCFCD Unit O100-00-00, to Wade Road Ditch No. 7, a Tributary within the Goose Creek Watershed - HCFCD Unit O112-00-00-X002 Entire channel, from confluence with Goose Creek, HCFCD Unit O100-00-00, to Wade Road 

Tributary of the San Jacinto Bay - HCFCD Unit F101-06-00-X004 Lomax School Road to upstream of the confluence with HCFCD Unit F101-00-00 

Tributary within the Carpenters Bayou Watershed - HCFCD Unit N104-00-00-X010 From near Vonnet Street to Woodforest Boulevard Tributary within the Carpenters Bayou Watershed - HCFCD Unit N104-00-00-X008 Avenue C to the Union Pacific Railroad tracks 

Tributary within the Sims Bayou Watershed - HCFCD Unit C106-10-01-X008 From its confluence with HCFCD Unit C106-10-00 near Bronson Street to Minnesota Street