2018 Bond Program

As of 08/15/2019

Recent Action on Bond Projects

The table below provides information about recent Harris County Commissioners Court action and other milestones for Bond Program projects. The Bond Project Map ID corresponds to the Map ID number on the Bond Program Project List and map. Click on the Bond Project Map ID to read more about the project.

 > Learn More About the Bond Program Project List

Watershed Bond Project Map ID Project Description Recent Action
County-wide > Z-01 County-wide Floodplain Preservation and Right-of-Way Acquisition April 30, 2019 – Harris County Commissioners Court authorized and initiated this project under the Z-01 Bond Map ID Number, and transferred ongoing county-wide general acquisition projects to this bond-funded project
County-wide > Storm Repairs Repairs to channels and other drainage infrastructure damaged during Harvey April 9, 2019 -- Harris County Commissioners Court awarded five construction contracts totaling approximately $22.1 million for Harvey repair projects in the Spring Creek, Cypress Creek and Willow Creek watersheds.

October 9, 2018 -- Harris County Commissioners Court awarded an additional construction contract for $799,079 for Harvey repair projects in the Little Cypress Creek watershed. Construction is expected to begin on some project sites in late 2018, and to be completed in 2019.

September 25, 2018 -- Harris County Commissioners Court awarded two more construction contracts totaling approximately $1.7 million for Harvey repair projects in the Greens Bayou and Addicks Reservoir watersheds.

September 11, 2018 -- Harris County Commissioners Court awarded four construction contracts totaling approximately $9.7 million for Harvey repair projects in the Cypress Creek, Greens Bayou and Addicks Reservoir watersheds.
County-wide > Z-02

*Assumed Bond Project Map ID pending Harris County Commissioners Court approval
Partnership projects with Municipalities, Authorities and Other Districts in Harris County
Countywide > Z-05

*Assumed Bond Project Map ID pending Harris County Commissioners Court approval
Aquifer Recharge Technology for Drainage Reuse

*This is one project under a wider Bond Project to examine Advanced Emerging Technologies for Flood Damage Reduction
February 12, 2019 – Harris County Commissioners Court approved a $621,900 contract with an engineering firm in support of Phase 2 of this project

January 29, 2019 – Harris County Commissioners Court authorized initiation of a project to examine aquifer recharge technology for drainage reuse
County-wide > Z-08 Preliminary Engineering for Large Diameter Tunnels for Stormwater Conveyance July 30, 2019 – Harris County Commissioners Court authorized an agreement with the San Antonio River Authority for information required in support of this project.

May 14, 2019 – Harris County Commissioners Court authorized a $400,000 agreement with an engineering firm to conduct a feasibility study in support of this project

April 30, 2019 – Harris County Commissioners Court authorized negotiations with an engineering firm for engineering and related consulting services in support of this project

February 26, 2019 – Harris County Commissioners Court authorized the Harris County Flood Control District to accept a $320,000 grant from the U.S. Department of Commerce, with a required local match of $80,000, in support of this project

June 26, 2018 -- Harris County Commissioners Court authorized the Harris County Flood Control District to apply for a grant from the U.S. Department of Commerce in support of this project
County-wide > Z-09 Upgrades and expansion of the Harris County Flood Warning System September 25, 2018 -- Harris County Commissioners Court authorized an interlocal agreement with Fort Bend County to install and maintain five additional gages as part of the system that measures rainfall and water levels in bayous and channels and reports this information to the public via www.harriscountyfws.org
County-wide > Z-10

*Assumed Bond Project Map ID pending Harris County Commissioners Court approval
A countywide flood hazard assessment with new rainfall data and advanced modeling technologies to provide more accurate information on flooding risks and contribute to revised Harris County floodplain maps February 12, 2019 – Harris County Commissioners Court awarded contracts for floodplain mapping and related engineering services in support of this project

January 29, 2019 -- Harris County Commissioners Court approved a $2.5 million contract with an engineering firm for engineering, project management and control, and quality control services in support of this project

September 25, 2018 -- Harris County Commissioners Court authorized the Harris County Flood Control District to accept a $6.5 million grant from the Federal Emergency Management Agency, with an $8 million local match; and to authorize negotiations with an engineering firm to provide surveying services in support of this project
County-wide Various

Hurricane Harvey Home Buyout Program
Voluntary Home Buyout program
Multi
(Harris County Engineering)
> E-Multiple Subdivision Drainage Projects October 9, 2018 – Harris County Commissioners Court authorized negotiations with engineering firms for preliminary engineering

August 28, 2018 – Harris County Commissioners Court authorized negotiations with engineering firms for preliminary engineering
Addicks Reservoir > Z-04

*Assumed Bond Project Map ID pending Harris County Commissioners Court approval
Stormwater Detention Basin at John Paul's Landing

*This is one project under a countywide Bond Project for Partnership projects with Harris County Engineering
February 26, 2019 – Harris County Commissioners Court approved a joint funding structure between Harris County and the Flood Control District for excavation of the central cell of this stormwater detention basin

January 29, 2019 – Harris County Commissioners Court authorized initiation of a partnership project with Harris County Engineering to build a stormwater detention basin at John Paul’s Landing
Addicks Reservoir > C-36 Channel conveyance improvements and bypass channel for South Mayde Creek, HCFCD Unit U101-00-00 October 9, 2018 – Harris County Commissioners Court authorized the County Judge to execute an agreement with the U.S. Army Corps of Engineers to allow the Flood Control District access to Addicks Reservoir property in support of this project

March 27, 2018 Harris County Commissioners Court approved a $495,000 agreement for engineering services in support of this project.
Addicks Reservoir > C-37 Little York Stormwater Detention Basin July 30, 2019 – Harris County Commissioners Court authorized negotiations with an engineering firm for materials engineering and testing services in support of this project

February 26, 2019 – Harris County Commissioners Court authorized negotiations with the Cypress—Fairbanks Independent School District in support of this project

December 18, 2018 – Harris County Commissioners Court approved an agreement with Harris County Municipal Utility District No. 166 in support of this project

October 23, 2018 – Harris County Commissioners Court authorized negotiations with Harris County Municipal Utility District No. 166 in support of this project
Addicks Reservoir > C-46 Right-Of-Way Acquisition, Design and Construction of a Stormwater Detention Basin on South Mayde Creek, HCFCD Unit U501-06-00 On March 26, Harris County Commissioners Court approved a $500,000 contract with an engineering firm to conduct preliminary engineering in support of this project

November 13, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm for preliminary engineering services in support of this project

September 25, 2018 – Harris County Commissioners Court authorized and initiated this project
Addicks Reservoir > F-53 De-silting of 17 drainage channels that drain into Addicks Reservoir November 13, 2018 – Harris County Commissioners Court approved a $3.9 million agreement with an engineering firm for final design of this project

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm for final design of this project
Addicks Reservoir > F-56 Investigation of multiple stormwater storage areas within the upper Cypress Creek and Addicks Reservoir watersheds February 26, 2019 – Harris County Commissioners Court authorized a $360,000 agreement with an engineering firm for a feasibility investigation in support of this project

September 25, 2018 -- Harris County Commissioners Court authorized negotiations with an engineering firm to conduct an engineering investigation in support of this project

September 25, 2018 – Harris County Commissioners Court authorized and initiated a project to investigate multiple stormwater storage areas within the upper Cypress Creek and Addicks Reservoir watersheds.
Addicks Reservoir > F-83 Stormwater Detention Basin for the Upper Langham Creek Frontier Program October 23, 2018 – Harris County Commissioners Court authorized and initiated this project
Addicks Reservoir > F-112 Final design of a wetlands mitigation bank, HCFCD Unit U700-01-00 December 4, 2018 -- Harris County Commissioners Court approved a $120,000 agreement with an engineering firm for specialized evaluation and design services in support of this project.

October 9, 2018 – Harris County Commissioners Court authorized negotiations with an environmental firm for specialized evaluation and design services in support of this project

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Armand Bayou > CI-021 Flood risk reduction project on Willow Springs Bayou, HCFCD Unit B112-00-00 and Tributary B112-02-00 in the Brookglen subdivision of La Porte January 8, 2019 – Harris County Commissioners Court approved a $250,000 agreement with an engineering firm in support of this project

September 25, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to conduct an engineering investigation in support of this project

September 25, 2018 – Harris County Commissioners Court authorized and initiated this project
Armand Bayou > CI-023 Channel conveyance improvements along Horsepen Bayou, HCFCD Unit B104-00-00, and its tributaries in the Armand Bayou watershed November 13, 2018 – Harris County Commissioners Court approved an $810,161 agreement with an engineering firm to conduct preliminary engineering support of this project

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to conduct preliminary engineering in support of this project

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Armand Bayou > F-72 Baywood Stormwater Detention Basin, HCFCD Unit B513-02-00, in the Armand Bayou watershed November 13, 2018 – Harris County Commissioners Court approved a $578,957 agreement with an engineering firm to conduct preliminary engineering in support of this project

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to conduct preliminary engineering and final design in support of this project

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Armand Bayou > F-96 Watershed Feasibility Study for Armand Bayou May 14, 2019 – Harris County Commissioners Court authorized and initiated this project.
Barker Reservoir > F-52 De-silting of 13 drainage channels within Harris County that drain into Barker Reservoir December 4, 2018 -- Harris County Commissioners Court approved a $3,556,000 agreement with an engineering firm for final design of this project.

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm for final design of this project
Buffalo Bayou, Addicks Reservoir, Barker Reservoir > C-40 U.S. Army Corps of Engineers Section 216 study of Addicks and Barker reservoirs operations and effectiveness October 9, 2018 – Harris County Commissioners Court authorized the County Judge to execute a feasibility cost-sharing agreement with the Department of the Army in support of this study

September 25, 2018 -- Harris County Commissioners Court authorized the execution of a document certifying the Harris County Flood Control District’s financial ability to participate as a local sponsor of this project
Brays Bayou > Z-02

*Assumed Bond Project Map ID pending Harris County Commissioners Court approval
Stormwater detention on City of Houston right-of-way at South Braeswood Boulevard and West 610 Loop

*This is one project under a countywide Bond Project for Partnership Projects with Municipalities, Authorities, and Other Districts in Harris County
August 13, 2019 – Harris County Commissioners Court authorized a $351,000 agreement with the City of Bellaire in support of this study. The City of Bellaire, Texas in the amount of $351,000 to conduct a drainage and flood control study of the Brays Bayou Watershed on Unit D100-00-00 in the Brays Bayou Watershed in Precinct 3 (Project ID D100-00-00-P011).

April 30, 2019 – Harris County Commissioners Court authorized a $224,960 contract with an engineering firm for design, bidding, and construction phase engineering services for construction of detention basins on City of Houston right-of-way at South Braeswood Boulevard and West 610 Loop

March 12, 2019 -- Harris County Commissioners Court authorized negotiations with an engineering firm for design, bidding and construction phase engineering services in connection with this project

January 29, 2019 – Harris County Commissioners Court authorized negotiations with the City of Houston for stormwater detention on City of Houston right-of-way at South Braeswood Boulevard and West 610 Loop.
Brays Bayou > C-11 Federal Flood Damage Reduction Project December 18, 2018 -- Harris County Commissioners Court authorized the County Judge to execute an amendment to the Flood Control District Project Partnership Agreement with the U.S. Army Corp of Engineers that will allow the Corps to fully reimburse the Flood Control District for any work on the Brays Bayou federal project after February 9, 2018. Previous partial reimbursements for $28 million in work completed before that date are ongoing and are still subject to annual federal appropriations.
Brays Bayou > C-12 Conveyance Improvements on Poor Farm Ditch September 11, 2018 -- Harris County Commissioners Court authorized an application to the Texas Department of Public Safety for a grant in support of this project
Brays Bayou > C-13 Final design of conveyance improvements on Bintliff Ditch D133-00-00 October 23, 2018 – Harris County Commissioners Court authorized and initiated this project
Brays Bayou > F-08 Fondren Diversion Channel September 25, 2018 – Harris County Commissioners Court authorized and initiated this project
Buffalo Bayou > CI-014

Combined with Bond Project F-81
Flood risk reduction project on Buffalo Bayou tributaries, HCFCD Units W151-00-00 and W153-00-00 November 13, 2018 – Harris County Commissioners Court approved an $827,264 agreement with an engineering firm to conduct preliminary engineering in support of this project

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to conduct preliminary engineering in support of this project

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Buffalo Bayou > F-81

Combined with Bond Project CI-014
Flood risk reduction project on Buffalo Bayou tributaries, HCFCD Units W151-00-00 and W153-00-00 November 13, 2018 – Harris County Commissioners Court approved an $827,264 agreement with an engineering firm to conduct preliminary engineering in support of this project

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to conduct preliminary engineering in support of this project

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Buffalo Bayou > F-82 Demolition of Structure at 1119 Commerce Street February 26, 2019 – Harris County Commissioners Court authorized and initiated this project
Buffalo Bayou > CI-016 Study to evaluate how bridges over Buffalo Bayou affect stormwater flow and whether high-flow bypasses would improve conveyance. November 13, 2018 – Harris County Commissioners Court approved a $350,000 agreement with an engineering firm to conduct this study

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to conduct this study

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Cedar Bayou > F-44 Flood risk reduction alternatives analysis of Cedar Bayou Tributary Q130-00-00 April 9, 2019 – Harris County Commissioners Court approved a $700,000 contract with an engineering firm for a detailed flood risk reduction alternatives analysis in support of this project.

November 13, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Cedar Bayou > F-45

Combined with Bond Project F-68
Flood risk reduction alternatives analysis of Cedar Bayou Tributary Q134-00-00 and Q134-01-00 April 9, 2019 – Harris County Commissioners Court approved an $850,000 contract with an engineering firm for a detailed flood risk reduction alternatives analysis in support of this project.

November 13, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm

November 13, 2018 – Harris County Commissioners Court authorized and initiated this project
Cedar Bayou > F-68

Combined with Bond Project F-45
Flood risk reduction alternatives analysis of Cedar Bayou Tributary Q134-00-00 and Q134-01-00 November 13, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm in support of this project

November 13, 2018 – Harris County Commissioners Court authorized and initiated this project
Cedar Bayou > F-48 Crosby Eastgate Environmental Mitigation Bank August 28, 2018 -- Harris County Commissioners Court authorized an amendment to a 2017 agreement with an engineering firm for specialized environmental services in support of this project.
Cedar Bayou > F-123 Watershed-Wide Bond Implementation Program for Cedar Bayou Projects June 25, 2019 – Harris County Commissioners Court authorized a $449,190 agreement with an engineering firm to research and develop an implementation plan for the Cedar Bayou watershed bond projects

May 14, 2019 – Harris County Commissioners Court authorized negotiations with an engineering firm to assist with a watershed-wide implementation program for Cedar Bayou projects
Clear Creek > C-03 Federal Flood Damage Reduction Project July 30, 2019 – Harris County Commissioners Court authorized an additional $1.9 million for surveying services in support of this project

May 14, 2019 – Harris County Commissioners Court authorized negotiations with an engineering firm for hydrologic and hydraulic services in support of this project

May 14, 2019 – Harris County Commissioners Court authorized the execution of a document certifying the Harris County Flood Control District’s financial ability to participate as a local sponsor of this project

October 9, 2018 -- Harris County Commissioners Court authorized the County Judge to execute an agreement with a consultant for surveying services in support of this project
Clear Creek > C-05 Phase 3 design and construction of the South Belt Stormwater Detention Basin, HCFCD Unit A520-03-00 December 4, 2018 -- Harris County Commissioners Court approved a $188,180 agreement with an engineering firm for final design of this project.
Clear Creek > CI-001 Rehabilitation of the Clear Creek channel October 23, 2018 – Harris County Commissioners Court authorized and initiated this project
Clear Creek > CI-003 Channel conveyance improvements in the Clear Creek watershed October 23, 2018 – Harris County Commissioners Court authorized and initiated this project
Clear Creek > CI-013 Restoration of channel conveyance capacity on Clear Creek Tributary A104-00-00 November 13, 2018 – Harris County Commissioners Court authorized negotiations with the City of Shore Acres in support of this project

October 23, 2018 – Harris County Commissioners Court authorized and initiated this project
Clear Creek > CI-039 Partnership project with the City of Nassau Bay to reduce flooding risks January 29, 2019 – Harris County Commissioners Court approved a $125,000 interlocal agreement with the City of Nassau Bay in support of this project

December 18, 2018 – Harris County Commissioners Court authorized negotiations with the City of Nassau Bay in support of this project

October 23, 2018 – Harris County Commissioners Court authorized and initiated this project
Clear Creek > CI-62

Combined with Bond Project CI-63
Investigation to identify locations for new stormwater detention basins along lower Clear Creek, HCFCD Unit A100-00-00, near F.M. 528 and Dixie Farm Road November 13, 2018 – Harris County Commissioners Court approved a $260,000 agreement with an engineering firm for conduct an engineering investigation in support of this project

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to conduct an engineering investigation in support of this project

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Clear Creek > CI-63

Combined with Bond Project CI-62
Investigation to identify locations for new stormwater detention basins along lower Clear Creek, HCFCD Unit A100-00-00, near F.M. 528 and Dixie Farm Road November 13, 2018 – Harris County Commissioners Court approved a $260,000 agreement with an engineering firm for conduct an engineering investigation in support of this project

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to conduct an engineering investigation in support of this project

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Clear Creek > F-02 Hughes Stormwater Detention Basin August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Clear Creek > F-03 Final design for Dagg Road Stormwater Detention Basin, HCFCD Unit A500-08-00, in the Clear Creek watershed August 13, 2019 - Harris County Commissioners Court authorized negotiations with an engineering firm for materials engineering and testing services in support of this project.

Recommendation for authorization to negotiate agreements with:
HVJ Associates, Inc., for materials engineering and testing services for construction of the Dagg Road stormwater detention basin on Unit A500-08-00 in the Clear Creek Watershed in Precinct 1 (Map ID F-03, Project ID A500-08-00-E002).

July 30, 2019 – Harris County Commissioners Court authorized acceptance of a Preliminary Engineering Report in support of this project

November 13, 2018 – Harris County Commissioners Court approved a $428,051 agreement with an engineering firm for final design of this project

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm for final design of this project
Clear Creek > F-76 Final design of a wetlands mitigation bank, HCFCD Unit A700-01-00 December 4, 2018 -- Harris County Commissioners Court approved a $90,442 agreement with an environmental firm for specialized evaluation and planning services in support of this project.

October 9, 2018 – Harris County Commissioners Court authorized negotiations with an environmental firm for specialized evaluation and planning services in support of this project

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Cypress Creek > CI-012 Major maintenance on Cypress Creek May 14, 2019 – Harris County Commissioners Court approved a $5.82 million agreement with an engineering firm to provide watershed-wide engineering services in support of this project

March 26, 2019 – Harris County Commissioners Court authorized negotiations with an engineering firm to conduct design, bidding and construction stage engineering services in support of this project

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Cypress Creek > CI-035 Update the 2003 Texas Water Development Board Regional Drainage Plan for Major Tributaries of Cypress Creek June 25, 2019 – Harris County Commissioners Court authorized an additional $100,000 for engineering services in support of this project

November 13, 2018 – Harris County Commissioners Court approved a $600,000 agreement with an engineering firm for updates to the 2003 regional drainage plan and environmental investigations

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm for updates to the 2003 regional drainage plan and environmental investigations

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Cypress Creek > CI-36 Investigation of Additional Detention Volume at K500-01-00 Cypress Park Stormwater Detention Basin
Cypress Creek > CI-020 Investigation of Potential Detention Sites Around Cypress Creek and Stuebner Airline Road
Cypress Creek > F-20 Right-of-way acquisition and floodplain preservation October 23, 2018 – Harris County Commissioners Court authorized and initiated this project
Cypress Creek > F-23 Construction of Channel Conveyance Improvements Along K163-00-00 June 4, 2019 – Harris County Commissioners Court approved a revised preliminary engineering report and authorized proceeding to design and construction of the revised channel conveyance improvements.

June 4, 2019 – Harris County Commissioners Court authorized an additional $445,068 agreement with an engineering firm for design, bidding, and construction phase engineering services in support of this project
Greens Bayou > C-20 Mid-Reach channel conveyance improvements August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Greens Bayou > C-31 Final design of the Smith Road Channel Diversion Project on Garners Bayou Tributaries, HCFCD Units P133-00-00 and P133-06-00 December 4, 2018 – Harris County Commissioners Court approved a $43,864 amendment to the agreement for engineering services in support of this project (2018 Bond Program funded)

May 22, 2018– Harris County Commissioners Court authorized a $446,078 agreement with an engineering firm for design, bidding and construction phase services in connection with this project (funded from the HCFCD Capital Improvements Program)
Greens Bayou > C-32 Final design for Cutten Road Stormwater Detention Basin, HCFCD Unit P500-02-00 November 13, 2018 – Harris County Commissioners Court approved a $739,525 agreement with an engineering firm for final design of this project

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm for final design of this project
Greens Bayou > C-33 Aldine-Westfield Stormwater Detention Basin, HCFCD Unit P500-04-00 July 30, 2019 – Harris County Commissioners Court authorized an agreement with an engineering firm for an additional $185,020 in engineering services in support of this project

March 26, 2019 – Harris County Commissioners Court awarded a $6.85 million contract for construction of this project

January 29, 2019 – Harris County Commissioners Court approved a $49,976 agreement with an engineering firm for materials engineering and testing services in support of this project

December 18, 2018 – Harris County Commissioners Court authorized an $100,000 amendment to a previous $543,000 agreement with an engineering firm to provide final design of this project

October 9, 2018 – Harris County Commissioners Court authorized negotiations with a consultant for materials engineering and testing services in support of this project
Greens Bayou > C-34 Lauder Stormwater Detention Basin, HCFCD Unit P500-06-00 June 25, 2019 – Harris County Commissioners Court authorized negotiations with an engineering firm for design, bidding and construction stage engineering services in connection with Phase 2 of this project.

May 14, 2019 – Harris County Commissioners Court authorized the purchase of wetlands mitigation credits from the Greens Bayou Wetlands Mitigation Bank in support of this project.
Greens Bayou > F-40 Lower Greens Bayou Stormwater Detention Basin, HCFCD Unit P500-01-00, embankment and control structure improvements January 29, 2019 – Harris County Commissioners Court approved a $92,921 agreement with an engineering firm for materials engineering and testing services in support of this project.

December 4, 2018 – Harris County Commissioners Court approved a $2.4 million contract for construction of this project

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to conduct materials engineering and testing services in support of this project
Greens Bayou > Z-02

*Assumed Bond Project Map ID pending Harris County Commissioners Court approval
Drainage improvements in the Greenwood Forest Subdivision April 30, 2019 – Harris County Commissioners Court authorized a $360,625 agreement with Harris County Water Control & Improvement District No. 109 in connection with a project to construct drainage improvements to Green Springs Drive and Pinewood Springs Drive in the Greenwood Forest Subdivision and a detention pond at Pinewood Springs Drive to reduce excess stormwater flow into Unit P152-00-00 in the Greens Bayou Watershed
Halls Bayou > C-01 Flood risk reduction in the drainage area of Halls Bayou Tributary P118-26-00 and related stormwater detention basins P518-26-01 and P518-26-02 July 30, 2019 – Harris County Commissioners Court authorized negotiations with an engineering firm for materials engineering and testing services in support of this project
Halls Bayou > C-25 Flood risk reduction in the drainage areas of Halls Bayou Tributary P118-21-00 February 26, 2019 – Harris County Commissioners Court authorized an agreement between Harris County Community Services, Harris County Precinct 2 and the Harris County Flood Control District using $9.58 million in Community Development Block Grant-Disaster Recovery program funds in support of this project

November 13, 2018 – Harris County Commissioners Court approved a $604,471 contract with an engineering firm for preliminary engineering of this project
Halls Bayou > C-21 Local cost share for U.S. Army Corps of Engineers Halls Bayou Study October 9, 2018 – Harris County Commissioners Court approved an $712,260 amendment to a previous $661,000 agreement with an engineering firm for an implementation and phasing plan in support of this study
Halls Bayou > C-26

Combined with Bond Project C-27
Flood risk reduction project within the drainage areas of HCFCD Units P118-23-00 and P118-23-02 November 13, 2018 – Harris County Commissioners Court approved an $864,985 agreement with an engineering firm to conduct preliminary engineering in support of this project

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to complete a preliminary engineering report in support of this project

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Halls Bayou > C-27

Combined with Bond Project C-26
Flood risk reduction project within the drainage areas of HCFCD Units P118-23-00 and P118-23-02 November 13, 2018 – Harris County Commissioners Court approved an $864,985 agreement with an engineering firm to conduct preliminary engineering in support of this project

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to complete a preliminary engineering report in support of this project

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Halls Bayou > C-28

Combined with Bond Project C-29
Flood risk reduction project within the drainage areas of HCFCD Units P118-25-00 and P118-25-01 November 13, 2018 – Harris County Commissioners Court approved a $900,000 agreement with an engineering firm to conduct preliminary engineering in support of this project

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to complete a preliminary engineering report in support of this project

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Halls Bayou > C-29

Combined with Bond Project C-28
Flood risk reduction project within the drainage areas of HCFCD Units P118-25-00 and P118-25-01 November 13, 2018 – Harris County Commissioners Court approved a $900,000 agreement with an engineering firm to conduct preliminary engineering in support of this project

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to complete a preliminary engineering report in support of this project

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Halls Bayou > C-35 Design and Construction of Stormwater Detention Basin and Associated Channel Improvement May 14, 2019 – Harris County Commissioners Court approved a $80,300 agreement with an engineering firm for additional design, bidding and construction stage engineering services in support of this project

March 26, 2019 – Harris County Commissioners Court authorized an application for Community Development Block Grant-DR funding in support of this project
Halls Bayou > F-122 Watershed Wide Bond Implementation Program for Halls Bayou Projects June 25, 2019 – Harris County Commissioners Court authorized a $400,000 agreement with an engineering firm to research and develop an implementation plan for Halls Bayou watershed bond projects

May 14, 2019 – Harris County Commissioners Court authorized negotiations with an engineering firm to assist with a watershed-wide implementation program for Halls Bayou projects
Hunting Bayou > C-18 Federal Flood Damage Reduction Project June 25, 2019 – Harris County Commissioners Court authorized an additional $101,270 for surveying services in support of the Hunting Bayou federal project

June 4, 2019 – Harris County Commissioners Court authorized a $279,191 addition in funding for design, bidding and construction phase engineering services in connection with additional channel improvements from U.S. 59 to the Homestead Stormwater Detention Basin outfall into Hunting Bayou as part of the Hunting Bayou Federal Flood Risk Management Project.

June 4, 2019 – Harris County Commissioners Court authorized a $80,990 addition in funding for design, bidding and construction phase engineering services in connection with additional channel improvements from upstream of Liberty Road to south of Wayside Drive as part of the Hunting Bayou Federal Flood Risk Management Project.

June 4, 2019 – Harris County Commissioners Court authorized negotiations with Union Pacific Railroad Company to facilitate design services in connection with the replacement of three railroad bridges over Hunting Bayou as part of the Hunting Bayou Federal Flood Risk Management Project.

March 12, 2019 – Harris County Commissioners Court authorized negotiations with an engineering firm for materials engineering and testing services in connection with a project to replace pedestrian bridges at Pickfair Street and Hoffman Street.

December 18, 2018 -- Harris County Commissioners Court authorized the County Judge to execute an amendment to the Flood Control District Project Partnership Agreement with the U.S. Army Corp of Engineers that will allow the Corps to fully reimburse the Flood Control District for any work on the Hunting Bayou federal project after February 9, 2018. Previous partial reimbursements for $19 million in work completed before that date are ongoing and are still subject to annual federal appropriations
Jackson Bayou > F-73 Watershed Feasibility Study for the Jackson Bayou Watershed May 14, 2019 – Harris County Commissioners Court authorized and initiated this project
Little Cypress Creek > C-19 Little Cypress Creek Frontier Program projects downstream of Cypress Rosehill Road May 14, 2019 – Harris County Commissioners Court approved a $1.59 million agreement with an engineering firm for preliminary engineering in support of a project from the confluence of Cypress Creek and Little Cypress Creek to Stablegate Subdivision

January 8, 2019 – Harris County Commissioners Court authorized negotiations with an engineering firm for final design of this project
Little Cypress Creek > F-26 Little Cypress Creek Frontier Program March 12, 2019 – Harris County Commissioners Court approved a $1.35 million agreement with an engineering firm for additional services needed to update the master plan and provide program management and staffing in support of this project

January 8, 2019 – Harris County Commissioners Court authorized negotiations with an engineering firm for final design of this project

December 18, 2018 – Harris County Commissioners Court formally accepted the Little Cypress Creek Watershed Master Drainage Plan and authorized the Flood Control District to proceed with implementation of the master plan, acquisition of right-of-way and design and construction of stormwater detention basins and channel improvements to reduce flooding risks in the Little Cypress Creek watershed
Little Cypress Creek > F-27 Zube Park Stormwater Detention Basin March 12, 2019 – Harris County Commissioners Court approved a $304,490 agreement with an engineering firm for Phase III design, bidding and construction stage engineering services in support of this project

December 18, 2018 – Harris County Commissioners Court accepted a preliminary engineering memo and authorized the Flood Control District to proceed with design and construction of this project
Little Cypress Creek > F-28 Kluge Stormwater Detention Basin
Little Cypress Creek > F-30 Schiel Stormwater Detention Basin March 26, 2019 – Harris County Commissioners Court approved a $2.23 million addition to a contract with an engineering firm to conduct design, bidding and construction stage engineering services in support of this project.

January 8, 2019 – Harris County Commissioners Court declared a public necessity and authorized the acquisition of three tracts of land in support of this project
Little Cypress Creek > F-31 Final design for Cypress Rosehill Stormwater Detention Basin, HCFCD Unit L500-10-00 March 26, 2019 – Harris County Commissioners Court approved a $1.6 million contract with an engineering firm to conduct preliminary engineering and design, bidding and construction stage engineering services in support of this project.

October 9, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm for final design of this project
Little Cypress Creek > F-32 Final design for Hegar Stormwater Detention Basin, HCFCD Unit L500-11-00 June 25, 2019 – Harris County Commissioners Court authorized the acquisition of seven tracts of land in support of this project.

March 26, 2019 – Harris County Commissioners Court approved a $1.96 million contract with an engineering firm to conduct preliminary engineering and design services in support of this project.

October 9, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm for final design of this project
Little Cypress Creek > F-33 Kleb Woods Stormwater Detention Basin Recent Action: June 4, 2019 – Harris County Commissioners Court authorized negotiations with an engineering firm for materials engineering and testing services in support of this project

January 8, 2019 – Harris County Commissioners Court authorized a $1,000 excavation and removal agreement in support of this project

December 18, 2018 – Harris County Commissioners Court accepted a Preliminary Engineering Report and authorized the Flood Control District to proceed with design and construction of this project
Little Cypress Creek > F-34 Final design for Mason Stormwater Detention Basin, HCFCD Unit L512-03-00 June 25, 2019 – Harris County Commissioners Court authorized the acquisition of nine tracts of land in support of this project.

March 26, 2019 – Harris County Commissioners Court approved a $1.53 million contract with an engineering firm to conduct preliminary engineering and design services in support of this project.

October 9, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm for final design of this project
Little Cypress Creek > F-35 Bauer-Hockley Stormwater Detention Basin May 14, 2019 – Harris County Commissioners Court awarded a $4.19 million contract for construction of this project

March 26, 2019 – Harris County Commissioners Court approved a $79,435 contract with an engineering firm for materials engineering and testing services in support of this project

December 18, 2018 – Harris County Commissioners Court accepted a Preliminary Engineering Report and authorized the Flood Control District to proceed with design and construction of this project

November 13, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to conduct materials engineering and testing services in support of this project
Luce Bayou > F-85 Watershed Feasibility Study for the Luce Bayou Watershed May 14, 2019 – Harris County Commissioners Court authorized and initiated this project
San Jacinto & Galveston Bay > C-58 Final design of Drainage Improvements Along HCFCD Unit F101-06-00 January 29, 2019 – Harris County Commissioners Court authorized initiation of this project
San Jacinto & Galveston Bay > F-101 Watershed Feasibility Study for the Galveston Bay Watershed May 14, 2019 – Harris County Commissioners Court authorized and initiated this project.
San Jacinto River > C-17 San Jacinto River Watershed Study July 30, 2019 – Harris County Commissioners Court authorized negotiations with Woodlands Municipal Utility District No. 1; Montgomery County Municipal Utility District Nos. 7, 46 and 60; and Harris-Montgomery Counties Municipal Utility District No. 386 for a partnership project to evaluate the feasibility of reservoirs in the Spring Creek Watershed to reduce flood risks on the San Jacinto River, HCFCD Unit G103-00-00, and Spring Creek, HCFCD Unit J100-00-00

March 12, 2019 – Harris County Commissioners Court approved a $2.71 million agreement with an engineering firm to conduct this watershed study

February 12, 2019 – Harris County Commissioners Court approved acceptance of a $2.03 million grant from the Federal emergency Management Agency, with a $677,052 required Flood Control District match

February 12, 2019 – Harris County Commissioners Court approved a $203,116 agreement with Montgomery County, the San Jacinto River Authority and the City of Houston in support of this study

September 25, 2018 -- Harris County Commissioners Court authorized a grant application to the Federal Emergency Management Agency in support of this project
San Jacinto River > F-14 Drainage improvements near Kingwood August 13, 2019 - Harris County Commissioners Court authorized a $700,000 agreement with an engineering firm for engineering services in support of this project. Neel-Schaffer, Inc., in the amount of $700,000 for engineering services to identify flooding sources and develop potential flooding solutions in the Kingwood area in Precinct 4 (Map ID F-14, Project ID Z100-00-00-P027, UPIN 190900Z1P027).

June 25, 2019 – Harris County Commissioners Court authorized negotiations with an engineering firm to identify flooding sources and develop potential solutions in the Kingwood area.

June 4, 2019 – Harris County Commissioners Court authorized an agreement with the Lake Houston Redevelopment Authority/Tax Increment Reinvestment Zone No. 10 to conduct an evaluation of channel capacities and possible improvements within Kingwood, with no Flood Control District funding required

March 26, 2019 – Harris Harris County Commissioners Court authorized negotiations with the Lake Houston Redevelopment Authority in support of this project

October 23, 2018 – Harris County Commissioners Court authorized and initiated this project
San Jacinto River > F-110 Drainage improvements in the Huffman area that drain to the San Jacinto, Luce, and Cedar Bayou watersheds November 13, 2018 – Harris County Commissioners Court approved a $400,000 agreement with an engineering firm to conduct engineering investigation in support of this project

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to conduct an engineering investigation in support of this project

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Sims Bayou > C-09 Channel conveyance Improvements and stormwater detention basin on HCFCD Unit C147-00-00 December 18, 2018 – Harris County Commissioners Court authorized submission of a grant application to the U.S. Department of Homeland Security Pre-Disaster Mitigation Flood Risk Reduction Program in support of this project.

September 25, 2018 -- Harris County Commissioners Court authorized a $925,000 agreement with an engineering firm to conduct an engineering investigation in support of this project

May 1, 2018 -- Harris County Commissioners Court authorized submission of a grant application to the Federal Emergency Management Agency Hazard Mitigation Grant program in support of this project
Sims Bayou > C-10 South Shaver Stormwater Detention Basin February 26, 2019 – Harris County Commissioners Court authorized negotiations with the City of Houston in support of this project
Sims Bayou > CI-027 Drainage improvements along Berry Bayou Tributary C106-06-00 in the City of South Houston November 13, 2018 – Harris County Commissioners Court authorized the Flood Control District to negotiate an interlocal agreement with the City of South Houston in support of this project

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Spring Creek > F-19 Right-of-way acquisition and floodplain preservation October 23, 2018 – Harris County Commissioners Court authorized and initiated this project
Spring Creek > F-75 Watershed Feasibility Study for the Spring Creek Watershed May 14, 2019 – Harris County Commissioners Court authorized and initiated this project
Spring Gully/Goose Creek > F-39 Flood risk reduction alternatives analysis of Spring Gully/Goose Creek Tributary O119-00-00 and O200-00-00 June 4, 2019 – Harris County Commissioners Court authorized a $450,000 agreement with an engineering firm for a detailed flood risk reduction alternatives analysis evaluating the feasibility of using Highlands Reservoir for pass-through detention during higher storm events in the Goose Creek Watershed

November 13, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to conduct this analysis

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project
Spring Gully/Goose Creek > F-121 Watershed Feasibility Study for the Goose Creek Watershed May 14, 2019 – Harris County Commissioners Court authorized and initiated this project
Vince Bayou > F-78 Watershed Feasibility Study for the Vince Bayou Watershed May 14, 2019 – Harris County Commissioners Court authorized and initiated this project
White Oak Bayou > C-14 Federal Flood Damage Reduction Project December 18, 2018 -- Harris County Commissioners Court authorized the County Judge to execute an amendment to the Flood Control District Project Partnership Agreement with the U.S. Army Corp of Engineers that will allow the Corps to fully reimburse the Flood Control District for any work on the White Oak Bayou federal project after February 9, 2018. Previous partial reimbursements for $53 million in work completed before that date are ongoing and are still subject to annual federal appropriations.

U.S. Army Corps of Engineers long-term investment plan of July 2018 includes $45 million to complete the project
White Oak Bayou > C-16 Woodland Trails Stormwater Detention Basin September 25, 2018 – Harris County Commissioners Court authorized and initiated this project

September 25, 2018 – Harris County Commissioners Court authorized submission of an amended application to the Texas Department of Public Safety for a grant in support of this project
White Oak Bayou > C-59 Inwood Forest Stormwater Detention Basins August 13, 2019 - Harris County Commissioners Court accepted a Preliminary Engineering Report in support of this project. Recommendation for authorization to accept a preliminary engineering report prepared by Lockwood, Andrews & Newnam, Inc., and proceed with design and construction of Unit E500-21-00 Inwood Forest stormwater detention basin in the White Oak Bayou Watershed in Precinct 1 (Map ID C-59, Project ID E500-21-00-E001).

March 26, 2019 -- Harris County Commissioners Court approved a $1.27 million contract with an engineering firm for design, bidding and construction stage engineering services in support of this project
White Oak Bayou > CI-011 Partnership with City of Houston on engineering investigation to reduce flooding risks near Hidden Lake Townhomes December 18, 2018 – Harris County Commissioners Court authorized initiation of this project
White Oak Bayou > F-09 Little White Oak Bayou channel conveyance improvements May 14, 2019 – Harris County Commissioners Court approved a $1.3 million agreement with an engineering firm to identify and evaluate watershed-wide flood risk reduction alternatives

February 26, 2019 – Harris County Commissioners Court authorized negotiations with an engineering firm

October 23, 2018 – Harris County Commissioners Court authorized and initiated this project
White Oak Bayou > F-10 Flood risk reduction project on Brickhouse Gully, HCFCD Unit E115-00-00 September 25, 2018 -- Harris County Commissioners Court authorized an interlocal agreement with the City of Houston for joint funding of an engineering investigation in support of this project
Willow Creek > F-37 Conveyance improvements along HCFCD Unit M124-00-00, from State Highway 249 to Willow Creek July 30, 2019 – Harris County Commissioners Court authorized a $1.6 million agreement with an energy company to adjust pipelines in connection with this project

April 30, 2019 – Harris County Commissioners Court authorized the Harris County Flood Control District to submit an application to the U.S. Department of Commerce/Economic
Development Administration for a $3 million grant, with a required match of $3.5 million, for the Willow Creek Stormwater Detention Basin project

November 13, 2018 – Harris County Commissioners Court approved a $901,245 agreement with an engineering firm to conduct preliminary engineering in support of this project

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm for preliminary engineering and final design of this project
Willow Creek > F-38 Cypress Rosehill Stormwater Detention Basin, HCFCD Unit M528-01-00 November 13, 2018 – Harris County Commissioners Court approved an $180,927 agreement with an engineering firm for final design and construction of this project

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to complete final design of this project
Willow Creek > F-71 Watershed Feasibility Study for the Willow Creek Watershed May 14, 2019 – Harris County Commissioners Court authorized and initiated this project