Construction Update: T.C. Jester Stormwater Detention Basin

Construction Activities Starting Soon on the T.C. Jester Stormwater Detention Basin

The Harris County Flood Control District is expected to begin construction related activities on the east compartments of the T.C. Jester Stormwater Detention Basin project soon. The T.C. Jester Stormwater Detention Basin project within the Cypress Creek watershed consists of four compartments and will increase stormwater storage capacity along Cypress Creek.


East Compartments

The east side of the T.C. Jester Stormwater Detention Basin project includes three compartments (1A, 1B, and 2) across approximately 128 acres along T.C. Jester Boulevard, between Cypresswood Drive and Cypress Creek. Once constructed, the compartments on the east side of the project are expected to provide approximately 1,000 acre-feet of stormwater storage – that's roughly 1,000 football fields covered in one foot of water.

Funding:
The east compartments will be advertised for bids as two construction packages.
Compartment 1B: State community-directed funding ($12 million) secured by State Representative Sam Harless through the Texas Water Development Board, and Community Development Block Grant - Disaster Recovery funding ($20.8 million)
Compartments 1A & 2: Federal community-directed funding ($9.95 million) secured by Congressman Dan Crenshaw through Federal Emergency Management Agency, and the 2018 Bond Program ($2.5 million).

Anticipated Schedule:
East Compartment 1B:

• Design Completion: Q4 2025
• Bid Advertisement: Q4 2025
• Construction Start: Q2 2026
• Construction Completion: Q4 2028

East Compartments 1A & 2:
• Site Preparation: Q1 2026
• Design Completion: Q2 2026
• Bid Advertisement: Q3 2026
• Construction Start: Q4 2026
• Construction Completion: Q1 2028


West Compartment

The west side of the project is expected to consist of one large compartment on 44 acres and is anticipated to provide up to 200 acre-feet of stormwater storage.
Funding:
The west compartment will be advertised for bids under a single construction package.

• West Compartment: Community Development Block Grant – Mitigation funding ($16.4 million) and the 2018 Bond Program ($1 million).

Anticipated Schedule:

• Design Completion: Q3 2026
• Bid Advertisement: Q3 2026
• Construction Start: Q1 2027
• Construction Completion: Q4 2028


Submit a question or comment about this project!

Thank you to Commissioner Ramsey and the Precinct 3 team for their support of our work in this area.

The Flood Control District appreciates the support of our federal, state, and local partners as we continue implementing flood risk reduction projects across the Cypress Creek watershed.

Learn more about the T.C. Jester Stormwater Detention Basin project.

HCFCD Unit ID: K500-23-00 – Bond ID: Z-02