C-28 and C-29 P118-25-00 and P118-25-01

C-28 and C-29 P118-25-00 and P118-25-01
Menu

recent actions

November 13, 2018 – Harris County Commissioners Court approved a $900,000 agreement with an engineering firm to conduct preliminary engineering in support of this project 

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to complete a preliminary engineering report in support of this project 

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project

PROJECT DESCRIPTION

Flood risk reduction project within the drainage areas of Tributary P118-25-00 and Sub-Tributary P118-25-01

The goal of this project is to reduce flooding risks by improving the capacity of Halls Bayou Tributary P118-25-00 and Sub-Tributary P118-25-01 to convey stormwater during rain events.

Stage

This project is currently undergoing an Alternatives Analysis as part of the PRELIMINARY ENGINEERING stage. This stage of the project will result in a Preliminary Engineering Report with a recommended project that can be taken to Harris County Commissioners Court for approval and then advanced to the DESIGN stage. The PER may identify needed right-of-way acquisition, utility relocation and a preliminary cost estimate.

Location

Tributary P118-25-00 is located just upstream (west) of Hardy Toll Road with an approximate length of 0.7 miles and a drainage area of 100 acres. The modeled channel terminates at Aldine Mail Route Road but continues north as a simple roadside ditch. Sub-tributary P118-25-01 intersects P118-25-00 about 1,200 feet south of Aldine Mail Route Road.

Bond Project Listing

Bond Projects C-28 and C-29 are potential future Partnership projects with the City of Houston and Harris County. 

  • The total allocation for all stages of the C-28 P118-25-00 project is currently $18 million on the Bond Project List, of which approximately $16.2 million would be partnership funding, if granted, and $1.8 million would be local costs. 
  • The total allocation for all stages of the C-29 P118-25-01 project is currently $6 million on the Bond Project List, of which approximately $5.4 million would be partnership funding, if granted, and $600,000 would be local costs.

Bond Listing

List of 2018 Bond Projects


The Harris County Flood Control District has a significant number of flood damage reduction projects occurring all over Harris County as part of its on-going Capital Improvement Program (CIP), Operations and Maintenance, and the 2018 Bond Program. Click on the red and orange highlighted areas to learn about projects' details. Some early-stage projects are not highlighted in the map. The map will be updated when projects advance or when more information becomes available. 

• Maintenance Projects   
• Capital Projects

Project Lifecycle

Every flood damage reduction project is unique. Yet each project begins and ends, with common and predictable milestones along the way. Whether a project moves forward – and how quickly – depends on many factors, including the availability of funding at each milestone, shifting community priorities for flood damage reduction, and other changing circumstances (such as the price of trees or concrete) from year to year.

Read more...


Community Engagement Meeting

A Community Engagement Meeting for this project was held on November 11, 2019 at the Hardy Senior Center, 11901 W. Hardy Road in Houston.