Segment 4 Construction Updates

Hillcroft Ave Bridge

The Hillcroft Bridge was completed in Winter 2020/2021. The bridge project cost approximately $3,300,000.
Learn More...

Chimney Rock Rd Bridge

Construction on the Chimney Rock Rd bridge began in Winter 2020/2021 and is anticipated to be completed in Fall 2022. The bridge project will cost approximately $10,500,000.
Learn More...

South Rice Ave Bridge

Construction on the South Rice Ave bridge began in Spring 2021 and is anticipated to be completed in Fall 2022. The bridge project will cost approximately $10,500,000.
Learn More...


Segment 3 Construction Updates

Stella Link Rd Bridge

The Stella Link Road bridge was completed in Winter 2020/2021. The bridge project cost approximately $4,000,000.
Learn More...

Buffalo Speedway Bridge

The Buffalo Speedway Bridge was completed in Winter 2021/2022. The bridge project cost approximately $9,600,000.
Learn More...

Greenbriar Dr Bridge

The Greenbriar Drive Bridge was completed in Summer 2020. The bridge project cost approximately $4,800,000.
Learn More...


Segment 2 Construction Updates

Almeda Rd Bridge

Construction on the Almeda Rd Bridge began in Spring 2021, was completed in Summer 2022. The bridge project cost $7,700,000.

Learn More...

Ardmore St Bridge Update

The Ardmore Street bridge was completed in Winter 2020/2021. The bridge project cost approximately $4,000,000.
Learn More...

Calhoun Rd Bridge

Construction on the Calhoun Road Bridge began in Winter 2020/2021 and the bridge and channel work and is anticipated to be completed in Fall 2022. The channel work under the bridge will cost approximately $754,000.
Learn More...


Segment 1 Construction Updates

Telephone Rd Bridge

The Telephone Road Bridge was completed in Summer 2021. The bridge project cost approximately $9,100,000.
Learn More...

Lawndale St Bridge

The Lawndale Street Bridge was completed in Spring 2021 . The bridge project cost approximately $9,100,000.
Learn More...

Forest Hill Blvd Bridge

Construction for the Forrest Hill bridge was completed in Summer 2019. The final cost of this bridge was $5,048,868.24.
Learn More...

South 75th St Bridge

The South 75th Street Bridge was completed in Winter 2021/2022. The bridge project cost approximately $7,700,000.
Learn More...

Galveston Sub UPRR (Union Pacific Railroad) Bridge

The UPRR (Union Pacific Railroad) Bridge was completed in Winter 2021/2022. The bridge project cost approximately $1,300,000.
Learn More...