Segment 4 Construction Updates

Hillcroft Ave Bridge

The Hillcroft Bridge was completed in Winter 2020/2021. The bridge project cost approximately $3,300,000.
Learn More...

Chimney Rock Rd Bridge

Construction on the Chimney Rock Rd bridge began in Winter 2020/2021 and is anticipated to be completed in Fall 2021. The bridge project will cost approximately $10,300,000.
Learn More...

South Rice Ave Bridge

Construction on the South Rice Ave bridge began in Spring 2021 and is anticipated to be completed in Fall 2021. The bridge project will cost approximately $9,700,000.
Learn More...


Segment 3 Construction Updates

Stella Link Rd Bridge

The Stella Link Road bridge was completed in Winter 2020/2021. The bridge project cost approximately $4,000,000.
Learn More...

Buffalo Speedway Bridge

Construction on the Buffalo Speedway bridge began in Spring 2021 and is anticipated to be complete in Winter 2021/2022. The bridge project will cost approximately $9,600,000.
Learn More...

Greenbriar Dr Bridge

The Greenbriar Dr bridge began construction in the Summer of 2019 and was completed in Summer 2020. The bridge project cost approximately $4,800,000.
Learn More...


Segment 2 Construction Updates

Almeda Rd Bridge

Construction on the Almeda Rd Bridge began in Spring 2021, and is anticipated to be completed in one year. The bridge is currently closed for construction and is expected to reopen in Fall 2021, with all construction completed by Winter 2021/2022. The bridge project will cost approximately $7,700,000.

Learn More...

Ardmore St Bridge Update

The Ardmore Street bridge was completed in Winter 2020/2021. The bridge project cost approximately $4,000,000.
Learn More...

Calhoun Rd Bridge

Construction on the Calhoun Road Bridge began in Winter 2020/2021 and the bridge and channel work and is anticipated to be completed Winter 2021/2022. The channel work under the bridge will cost approximately $754,000.
Learn More...


Segment 1 Construction Updates

Telephone Rd Bridge

Construction on the Telephone Rd bridge began in Spring 2020 and is anticipated to be completed Summer 2021. The bridge project cost approximately $9,100,000.
Learn More...

Lawndale St Bridge

Construction on the Lawndale St. bridge began in Spring 2020 and was completed in Spring 2021. The bridge project cost approximately $9,100,000.
Learn More...

Forest Hill Blvd Bridge

Construction for the Forrest Hill bridge was completed in Summer 2019. The final cost of this bridge was $5,048,868.24.
Learn More...

South 75th St Bridge

Construction on the South 75 St. bridge began in Spring 2021, and is anticipated to be completed in Spring 2022. The bridge project will cost approximately $7,700,000.
Learn More...

Galveston Sub UPRR (Union Pacific Railroad) Bridge

Construction on the UPRR (Union Pacific Railroad) bridge began in Summer 2021 and is anticipated to be completed in Fall 2021. The bridge project will cost approximately $1,300,000.
Learn More...