CI-62 Stormwater Detention Basin Near FM 1959

CI-62 Stormwater Detention Basin Near FM 1959
Menu
Note: Bond ID CI-63 has been consolidated with Bond ID CI-62.

Recent Actions

December 1, 2020 - Harris County Commissioners authorized initiation of this project in conjunction with the Clear Creek Federal Program.

November 10, 2020 - Harris County Commissioners authorized the addition of a new Unit Number, A500-09-00, to the Flood Control District’s stormwater management system for identification purposes.

Project description

This project will design and construct a stormwater detention basin on Clear Creek near FM 1959, on property owned by the Flood Control District. The Flood Control District and the City of Pearland are currently exploring a partnership project on this site.

Location

Locator map A500-09-00


The basin will be located on an undeveloped site along the Clear Creek overbank at FM 1959.

Stage

This project is in the PRELIMINARY ENGINEERING stage. In this stage, engineers and environmental specialists develop and evaluate possible alternatives, prepare mitigation site plans, project specifications and detailed cost estimates.

Bond Project Listing

Bond Project CI-62 is categorized as a potential “Partnership” 2018 Bond Program project. The Bond Project List includes a total allocation of $20 million, with $5 million coming from the Bond Program.