Final design for Cypress Rosehill Stormwater Detention Basin, HCFCD Unit L500-10-00

Recent Actions

December 3, 2019 – Harris County Commissioners Court authorized the acquisition of nine tracts in support of this project 

October 9, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm for final design of this project. 

March 26, 2019 – Harris County Commissioners Court approved a $1.6 million contract with an engineering firm to conduct preliminary engineering and design, bidding and construction stage engineering services in support of this project.

The Harris County Flood Control District has a significant number of flood damage reduction projects occurring all over Harris County as part of its on-going Capital Improvement Program (CIP), Operations and Maintenance, and the 2018 Bond Program. Click on the red and orange highlighted areas to learn about projects' details. Some early-stage projects are not highlighted in the map. The map will be updated when projects advance or when more information becomes available. 

• Maintenance Projects   
• Capital Projects