F-35 Bauer-Hockley Stormwater Detention Basin

F-35 Bauer-Hockley Stormwater Detention Basin
Menu

Project Description

This project is part of the Little Cypress Creek Frontier Program, which focuses on the 52‑square-mile Little Cypress Creek watershed in northwest Harris County. This area, which is experiencing rapid development with construction of the Grand Parkway, lacks sufficient natural drainage to accommodate expected growth. By collaborating with landowners and developers, the program works to identify a large-scale, mutually beneficial plan for drainage that cost‑effectively maximizes stormwater mitigation, flood damage reduction and water quality, as well as opportunities for public recreational amenities and open space. 

The Bauer-Hockley basin project involves design and construction of a stormwater detention basin to reduce flooding risks in the Little Cypress Creek Watershed. This basin will help reduce existing flood levels and allow for future stormwater infrastructure improvements that will reduce the risk of flooding in this area. 

The 101-acre basin site is located north of the intersection of Bauer-Hockley and Becker roads in northwest Harris County. 

The basin site has been significantly excavated through previous excavation and removal contracts. Construction on Phase I of the ultimate basin began in August 2019 and is expected to be complete in Summer 2020. 

When complete, the basin is expected to hold a total of approximately 251 million gallons, or more than 770 acre-feet, of excess stormwater.  

Projects that are part of the Little Cypress Creek Frontier Program will be partially funded by the 2018 Bond Program. Development impact fees also support the frontier program. Bond Project F-35 is a “Local Only” bond project, which means there is no other funding partner at this time and construction costs will be paid with bond funding. 

Total allocation for this project is currently $3.85 million on the Bond Project List. 

Stormwater detention basins reduce flooding risks and damages during heavy rain events by safely storing excess stormwater and slowly releasing it back to the bayou when the threat of flooding has passed.

Recent Actions

December 17, 2019 – Harris County Commissioners Court approved an additional $8,625 for Phase 1 construction of this basin.

May 14, 2019 – Harris County Commissioners Court awarded a $4.19 million contract for construction of this project.

March 26, 2019 – Harris County Commissioners Court approved a $79,435 contract with an engineering firm for materials engineering and testing services in support of this project. 

December 18, 2018 – Harris County Commissioners Court accepted a Preliminary Engineering Report and authorized the Flood Control District to proceed with design and construction of this project. 

November 13, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm to conduct materials engineering and testing services in support of this project.


The Harris County Flood Control District has a significant number of flood damage reduction projects occurring all over Harris County as part of its on-going Capital Improvement Program (CIP), Operations and Maintenance, and the 2018 Bond Program. Click on the red and orange highlighted areas to learn about projects' details. Some early-stage projects are not highlighted in the map. The map will be updated when projects advance or when more information becomes available. 

• Maintenance Projects   
• Capital Projects

COMMUNITY ENGAGEMENT MEETING

A community engagement meeting was held on Wednesday, November 14, 2018.