May 19, 2020 - Harris County Commissioners Court approved new Bond ID added to the 2018 Bond Program List./p>

April 7, 2020 – Harris County Commissioner Court approved $9,497,490, for engineering services for Phase II of a management plan in support of this project.

June 25, 2019 – Harris County Commissioners Court authorized a $449,190 agreement with an engineering firm to research and develop an implementation plan for Cedar Bayou watershed bond projects.

May 14, 2019 – Harris County Commissioners Court authorized negotiations with an engineering firm to assist with a watershed-wide implementation program for Cedar Bayou projects.

Project Description

This local Bond Implementation Management (BIM) project will provide coordination of implementation and construction of projects in the Cedar Bayou watershed. Funding for project allocated from F-47 ($3.1M), F-46 ($3.1M), and F-43 ($3M).

The Harris County Flood Control District has a significant number of flood damage reduction projects occurring all over Harris County as part of its on-going Capital Improvement Program (CIP), Operations and Maintenance, and the 2018 Bond Program. Click the Project ID on the Map to learn about projects’ details. Some early-stage projects are not highlighted on the map. The map will be updated when projects advance or when more information becomes available.