Projects & Studies

As of 04/08/2019

RECENT ACTION: November 30, 2018 – Harris County Flood Control District authorized its consultant to start work on the scoped tasks for this study

CI-035, CI-36, CI-020

Regional drainage plan and environmental investigation for Major tributaries in the Cypress Creek watershed K100-00-00 Cypress Creek

Project Description

The goal of this work is to identify projects to reduce or eliminate existing flooding risks.

The three projects in this scope of work include:

  • An update to the 2003 Texas Water Development Board “Regional Drainage Plan and Environmental Investigation for Major Tributaries in the Cypress Creek Watershed,” Bond Project CI-035
  • An investigation of the potential benefit of expanding Cypress Park Stormwater Detention Basin, HCFCD Unit K500-01-00, Bond Project CI-36.

>Read more about this existing basin

  • An investigation of the potential benefit of possible stormwater detention sites near Cypress Creek and Stuebner Airline Road, Bond Project CI-020

Project StaGE

This project is in the engineering investigation or FEASIBILITY STUDY stage. This stage will result in the identification of major general components of a plan to address an identified flooding issue. These components can then be considered in detail in the PRELIMINARY ENGINEERING stage.

>Read more about the PROJECT LIFECYCLE

LOCATION

This project is located in the Cypress Creek watershed of north Harris County.

BOND PROJECT LISTING

Bond Projects CI-035, CI-36, and CI-020 are categorized as “Local Only” bond projects. This means there is no other funding partner at this time and total project costs would be paid with bond funding. The Bond Project List includes a combined allocation for these three projects of $600,000.

>Read more about the BOND PROJECT LIST

COMMUNITY ENGAGEMENT MEETING

Not yet scheduled

PROJECT MILESTONES

November 13, 2018 – Harris County Commissioners Court approved a $600,000 agreement with an engineering firm to complete this study update and investigations

August 28, 2018 – Harris County Commissioners Court authorized negotiations with an engineering firm in support of this project

August 28, 2018 – Harris County Commissioners Court authorized and initiated this project