Projects & Studies

UPDATE: Construction is complete on the Horsepen Creek (HCFCD Unit U106-00-00) project site. Construction continues on the Bear Creek (HCFCD Unit U102-00-00) project site. Design for the Langham Creek (HCFCD Unit U100-00-00) project site is complete and has been issued for construction beginning in October 2018. The Flood Control District has purchased and cleared property to provide construction access in connection with the U107-00-00 project site.

On November 13, 2018, Harris County Commissioners Court approved a $3.9 million agreement with an engineering firm for final design of a project to repair and remove silt from 17 additional channels that drain to Addicks Reservoir.

F-53 Rehabilitation of Channels Upstream of Addicks Reservoir

The Harris County Flood Control District has begun a major investigation of the current condition and capacity of all channels for which it has property rights that flow into Addicks Reservoir.

The goal of this project is to assess and repair impacts from recent flood events on channels that carry stormwater into the federal reservoirs. The project is limited to channels within Harris County and for which the Flood Control District has property rights. Rainfall within the 138-square-mile Addicks Reservoir watershed drains along 159 miles of open waterways, including Langham Creek and its major tributaries, such as South Mayde Creek (U101-00-00), Bear Creek (U102-00-00) and Horsepen Creek (U106-00-00).

This work effort began with a pilot project to remove sediment from four channels near Addicks Reservoir and to restore them to their design capacity, if found to be required. On January 30, 2018, Harris County Commissioners Court awarded a $13.32 million construction contract to Lecon Inc. for this pilot project. The four channels are:

  • Horsepen Creek, formally identified as HCFCD Unit U106-00-00, from near Hamstead Park Drive to the reservoir;
  • Bear Creek, HCFCD Unit U102-00-00, from Greenhouse Road to just inside the reservoir;
  • Langham Creek, HCFCD Unit U100-00-00, from State Highway 6 to the reservoir; and
  • HCFCD Unit U107-00-00, a Langham Creek tributary on the west side of the reservoir, near Hidden Springs Drive.

Results of the pilot project will be used to guide procedures and develop the budget for a wider effort in the Addicks Reservoir and Barker Reservoir watersheds. A goal of this effort is to determine a cost per mile of channel de-silted and repaired. This cost data will be used to plan the work and budget on the other 17 channels, using funds from the 2018 Bond Program.

Bond Project F-53, which involves the removal of silt from 17 channels that drain into Addicks Reservoir, is a “Local Only” bond project. This means there is no other funding partner at this time and total project costs would be paid with bond funding. Total allocation for this project is currently $30 million on the Bond Project List.

>Learn about the Project Lifecycle

>Read the full Bond Project List

Part of the Flood Control District’s overall maintenance program, this project follows the Tax Day 2016 and Hurricane Harvey storms, which sent record levels of sediment-laden stormwater through the channels leading into the reservoirs, and caused severe erosion in some areas. Deposited sediment can impede stormwater outfalls and reduce the capacity of channels to carry stormwater.

Addicks and Barker reservoirs were built in west Harris County by the U.S. Army Corps of Engineers after disastrous floods of 1929 and 1935. They are designed to temporarily hold back stormwater and prevent damages along Buffalo Bayou, downtown Houston and the Port of Houston. Both reservoirs provide substantial storage capacity.

The Corps owns, operates and maintains the reservoirs, including the operation of outlet facilities that control discharges from the reservoirs into Buffalo Bayou. Most Flood Control District easements end at the limits of the federal-owned land.