CI-034 Channel Improvements Upstream of Fondren Road

CI-034 Channel Improvements Upstream of Fondren Road
Menu

Recent Action

June 29, 2021 – Harris County Commissioners Court authorized $250,000 for a feasibility study for this project.

April 27, 2021 – Harris County Commissioners Court authorized the Flood Control District to negotiate for engineering services for a feasibility study to evaluate the benefits of channel modifications from Fondren Rd. to Gessner Rd.

December 15, 2020 – Harris County Commissioners Court authorized the initiation of this project.

May 19, 2020 – Harris County Commissioners Court approved updates to project details in the 2018 Bond Program List. Update adds the words "on Brays Bayou" to project title.

PROJECT DESCRIPTION

The study explores the feasibility of channel conveyance improvements along Brays Bayou from Fondren Road to US 59. The study was initiated in September 2021 to complete an analysis to understand flooding risk and identify causes of flooding and make recommendations to reduce that flooding risk.