Construction on the Forest Green Stormwater Detention Basin Phase 1 Project Begins Soon!

Construction crews will be accessing the site from FM 2100, just south of the intersection of FM 1960. Residents are urged to respect all warning signs.

About this Project
Phase 1 of the Forest Green Stormwater Detention Basin project is designed to provide approximately 247 acre-feet of stormwater storage capacity — that is roughly the equivalent of 247 football fields covered in one foot of water.

A stormwater detention basin temporarily holds stormwater during heavy rain events to help reduce the risk of flooding in the area.

Learn more about this project

Funding

  • The 2018 Bond Program allocated approximately $22 million for preliminary engineering and design.
  • The project is expected to receive up to $5 million in construction funding through an EPA State and Tribal Assistance Grant (EPA-STAG), administered through Representative Dan Crenshaw’s office.
  • The Forest Green Stormwater Detention Basin construction contract was awarded for approximately $10.5 million.
  • The project is located in Huffman in east Harris County.

Anticipated Schedule

  • Construction Start: Q2 2026
  • Construction Completion: Q4 2027

The Flood Control District appreciates the support of federal, state, and local partners as the implementation of flood risk reduction projects continues across the Cedar Bayou watershed.