White Oak Bayou Federal Flood Damage Reduction Project Update

The Harris County Flood Control District would like to provide the following update on the two remaining segments of the White Oak Bayou Federal Flood Damage Reduction Project.

E100-00-00-E005 (FM1960 to Hollister)
• Construction is underway!
• The notice to proceed and mobilization for E100-00-00-E005 took place in mid-December 2022 and construction began in early January 2023.
• The construction contract for this segment allows for 420 calendar days which means the project should be completed by early 2024.
• Trails within the project limits will remain closed for the duration of construction for the safety of the public and construction personnel. Please contact Houston Parks Board for details on closures and detours.

E100-00-00-E007 (Hollister to Cole Creek)
• The final remaining project segment was advertised for bids on March 31, 2023, under the new Project ID E100-00-00-E007 (formerly E100-00-00-E006).
• The Flood Control District anticipates construction beginning in summer 2023.
• Trails within the project limits will remain closed until the construction of this segment is complete for safety of the public and construction personnel. Please contact Houston Parks Board for details on closures and detours.
• In the interim, the Flood Control District will continue to manage maintenance concerns, including mowing and illegal disposal issues. Any issues or concerns can be reported at www.hcfcd.org/contactus.

Please visit www.hcfcd.org/C14 for White Oak Bayou Federal Flood Damage Reduction Project updates; or to leave a question or comment, click the “Submit A Comment” button located under the Project Description section.